From: Frank Lundy, P.E., County Engineer
           Mark Acreman, P.E., Assistant County Engineer
           Seth Peterson, P.E., Pre-Construction Manager
           Madison Steele, Parks Director

Submitted by:  Stacy Appleton, Design Tech III

______________________________________________________________________

 

ITEM TITLE

Title

Live Oak Landing / Bicentennial Park Pedestrian Bridge - Permission to Advertise

End

STAFF RECOMMENDATION

Recommendation

Take the following actions:

1) Approve the Purchasing Director to place a competitive bid for the Live Oak Landing / Bicentennial Park Pedestrian Bridge Project; and

2) Approve the Chairman to execute any project related documents.

End

BACKGROUND INFORMATION

 

Background:  This project is for the construction of a pedestrian bridge that will connect Live Oak Landing and Bicentennial Park creating ease of use for pedestrian activity and synergy between the uses allowing a great visitor experience and maximization of usage of both parks.

 

Previous Commission action/date: 

 

September 29, 2023 - The Commission adopted Resolution #2023-187 which adopted the Baldwin County Fiscal Year 2023-2024 Budget and approved the FY24 Project Decision Items which included the Live Oak Landing / Bicentennial Park Pedestrian Bridge using $800,000.00 of Gulf of Mexico Energy Security Act (GOMESA) funds for Construction.

 

August 17, 2021 - The Commission approved the agreement with Dewberry Engineers, Inc., for Engineering/Environmental/Design Services for a new pedestrian bridge which will connect Bicentennial Park and Live Oak Landing in the amount of 6.75% of construction cost for survey, structural design and permitting and 5.80% for CE&I cost. The estimated cost for the services is $150,891.16 which will be paid from GOMESA funds approved by the Commission on 01/19/2021.

 

June 15, 2021 - The Commission authorized staff to begin negotiations with Dewberry Engineers, Inc., so that a final award recommendation can be made to the Baldwin County Commission for Engineering/Environmental/Design Services for a new pedestrian bridge which will connect Bicentennial Park and Live Oak Landing.

 

March 16, 2021 - The Commission approved the attached Request for Qualifications (RFQ) for Engineering/Environmental/Design Services for a new pedestrian bridge which will connect Bicentennial Park and Live Oak Landing and authorized the Purchasing Director to advertise the Request for Qualifications.

 

January 19, 2021 - The Commission approved funding the Live Oak Landing Project using Gulf of Mexico Energy Security Act (GOMESA) funds allocating $1,200,000 for Engineering, Environmental, Design Services and Construction

 

FINANCIAL IMPACT

 

Total cost of recommendation:  Actual Cost to be determined once bids are opened.

 

Budget line item(s) to be used:  HW24088.4CONTRCN.4CONTRSRV.4ADVERTISE

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up:  Highway Design staff will submit advertisement to Wanda Gautney, Purchasing Director, when plans and contract documents are finalized. Purchasing Director will then advertise project for competitive bid.

 