Agenda item title: Construction of Miscellaneous Protective Partitions at Various Buildings for the Baldwin County Commission
Attachments: 1. Certificate of Substantial Completion, 2. Summary of Previous ARPA Commission Action

Meeting Type:   BCC Regular Meeting

Meeting Date:  5/20/2025

Item Status:   New

From: Wanda Gautney, Purchasing Director; Patrick Addison, Architect PH&J; Brian Underwood, Grants Director; Buford King, Director of Facilities and Maintenance

Submitted by:  Jeanette Brown, Assistant Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Construction of Miscellaneous Protective Partitions at Various Buildings for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Approve and authorize the Chairman to execute the Certificate of Substantial Completion on the Construction of Miscellaneous Protective Partitions at Various Buildings.

End

BACKGROUND INFORMATION

 

Background:  The Architect, Patrick Addison with PH&J Architects, Inc., is submitting for Commission approval the Certificate of Substantial Completion on the Construction of Miscellaneous Protective Partitions at Various Buildings. The contractor has several minor items remaining on the punch list that will be completed prior to receiving final payment.

 

See attached Summary of Previous ARPA Commission Action.

 

Previous Commission action/date: 

05/06/2025 meeting: Approved and authorized the Chairman to execute Change Order #1 with TripTek Construction, LLC, in the credit amount of ($10,000.00) on the Construction of Miscellaneous Protective Partitions at Various Buildings.

 

07/02/2024 meeting: 1) Awarded the bid for the Miscellaneous Protective Partitions at Various Buildings to the lowest bidder, TripTek Construction, LLC, in the bid amount of $253,200.00, Construction Time: 180 days (Sundays & Holidays included); and 2) Authorized the Chairman to execute the Contract.

 

01/17/2023 meeting: Approved and authorized the Chairman to execute the Professional Services Contract with PH & J Architects, Inc., in the amount of 6.5% of the construction cost for the Design of Protective Partitions in various Baldwin County Commission facilities. (Funding will be from the American Rescue Plan Act (ARPA funds).

 

FINANCIAL IMPACT

 

Total cost of recommendation:  N/A

 

Budget line item(s) to be used:  N/A

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  05/20/2025

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 