File #: 25-1042    Version: 1
Agenda section: Consent Status: Agenda Ready
File created: 7/29/2025 Meeting type: Baldwin County Commission Regular
On agenda: 8/19/2025 Final action:
Agenda item title: Project No. HW25075 - Intersection Improvements on County Road 26 (West Michigan Avenue) and Hickory Street South for the Baldwin County Commission
Attachments: 1. Engineer Award Recommendation Letter, 2. Certified Bid Tabulation, 3. Contract - Rob Middleton Construction, LLC, 4. Proof of Advertisement

Meeting Type:   BCC Regular Meeting

Meeting Date:  8/19/2025

Item Status:   New

From: Wanda Gautney, Purchasing Director; Mark Acreman, Assistant County Engineer; Seth Peterson, Pre-Construction Manager

Submitted by:  Wanda Gautney, Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Project No. HW25075 - Intersection Improvements on County Road 26 (West Michigan Avenue) and Hickory Street South for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Award the bid for Project No. HW25075 - Intersection Improvements on County Road 26 (West Michigan Avenue) and Hickory Street South to the lowest bidder, Rob Middleton Construction, LLC, in the Bid Amount $2,100,221.80; Construction Time: 120 working days; and authorize the Chairman to execute the Contract.

 

End

BACKGROUND INFORMATION

 

Background:  Bids were opened in the Purchasing Conference Room on July 24, 2025, at 2:00 p.m. Nine (9) bids were received. Upon inspection by staff, the following mathematical errors were noted: Rob Middleton Construction, LLC, (-$251.28), Asphalt Services, Inc., (-$215.25), Grant Nichols Construction, LLC, (-$427.35), and Gibson Construction Services, LLC, (-$409.85). These errors did not change the overall outcome of the lowest bidder. The lowest bid was received from Rob Middleton Construction, LLC, in the bid amount of $2,100,221.80. The Baldwin County Assistant Engineer, Mark Acreman, reviewed the bid responses and submitted the Certified Bid Tabulation and a letter recommending that the bid be awarded to the lowest bidder, Rob Middleton Construction, LLC. Certified Bid Tabulation attached.

 

Highway will transfer $382,221.80 of FY 2024 Highway funds from the completed Project HW22146 - Old Foley Road at U.S. Highway 98 Intersection Improvements, to Project HW25075 - CR 26 at Hickory Street Improvements project to cover the overage in bid amount..

 

Previous Commission action/date:  05/20/2025 meeting: 1) Approved an Intergovernmental Service Agreement between the Baldwin County Commission and the City of Foley for the Intersection Improvement Project at County Road 26 (W Michigan Avenue) and S Hickory Street; and 2) Approved the Purchasing Director to place a competitive bid for the project once plans and specifications are completed.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $2,100,221.80

 

Budget line item(s) to be used:  HW25075.4CONTRCN .4CONTR SRV.4CONTRACT

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

Standard County Construction Contract

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  Yes

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  08/19/2025

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 