Legislation Details

File #: 26-0863    Version: 1
Agenda section: Consent Status: Agenda Ready
File created: 6/8/2026 Meeting type: Baldwin County Commission Regular
On agenda: 6/16/2026 Final action:
Agenda item title: Project No. HW24115 - Planting, Irrigation and Lighting Improvements at Lillian Boat Launch for the Baldwin County Commission
Attachments: 1. Engineer Award Recommendation Letter, 2. Certified Bid Tabulation, 3. Contract, 4. Proof of Publication
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Meeting Type:   BCC Regular Meeting

Meeting Date:  6/16/2026

Item Status:   New

From: Wanda Gautney, Purchasing Director; Mark Acreman, Assistant County Engineer; Seth Peterson, Pre-Construction Manager

Submitted by:  Jeanette Brown, Assistant Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Project No. HW24115 - Planting, Irrigation and Lighting Improvements at Lillian Boat Launch for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Award the bid for Project No. HW24115 - Planting, Irrigation and Lighting Improvements at Lillian Boat Launch to Coastal Contractors and Renovations, LLC, in the Bid Amount $232,950.00; Construction Time: 60 working days; and authorize the Chairman to execute the Contract.

 

End

BACKGROUND INFORMATION

 

Background:  Bids were opened in the Purchasing Conference Room on June 3, 2026, at 2:00 p.m. One (1) bid was received. The bid was received from Coastal Contractors and Renovations, LLC, in the bid amount of $232,950.00. The Assistant County Engineer, Mark Acreman, reviewed the bid response and submitted the certified Bid Tabulation and a letter recommending that the bid be awarded to Coastal Contractors and Renovations, LLC. Certified Bid Tabulation attached for review.

 

Previous Commission action/date:  02/19/2026 meeting: 1) Approved the Purchasing Director to place a competitive bid for Lillian Park Lighting and Landscaping project; and 2) Approved the Chairman to execute any project related documents.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $232,950.00

 

Budget line item(s) to be used:  HW24115.4CONTRCN .4CONTR SRV.4CONTRACT

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

Standard County Construction Contract

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  Yes

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  06/16/2026

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Bidder

 

Additional instructions/notes:  N/A