ITEM TITLE
Title
Project No. HW22146 - U.S. Highway 98 at Old Foley Road Intersection Realignment for the Baldwin County Commission
End
STAFF RECOMMENDATION
Recommendation
Approve Change Order #1 in the amount of $5,100.00 with Asphalt Services, Inc., for Project No. HW22146 - U.S. Highway 98 at Old Foley Road Intersection Realignment and authorize the Chairman to execute the Change Order.
End
BACKGROUND INFORMATION
Background: The Highway Department is submitting for Commission approval Change Order #1 in the amount of $5,100.00 for Project No. HW22146 - U.S. Highway 98 at Old Foley Road Intersection Realignment. The County had to get the Contractor to add additional slope paving and concrete curbs in order to comply with ALDOT permit requirements.
Previous Commission action/date:
10/01/2024 meeting: Awarded the bid for Project No. HW22146 - U.S. Highway 98 at Old Foley Road Intersection Realignment to the lowest bidder, Asphalt Services, Inc., in the Bid Amount $461,310.25; Construction Time: 45 working days; and authorized the Chairman to execute the Contract.
07/02/2024 meeting: 1) Authorized the Purchasing Director to place a competitive bid for the U.S. Highway 98 at Old Foley Road Intersection Improvements Project; and 2) Authorized the Chairman to execute any project related documents.
FINANCIAL IMPACT
Total cost of recommendation: $5,100.00
Budget line item(s) to be used: HW22146.4CONTRCN .4CONTR SRV. 4CONTRACT
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
N/A
Reviewed/approved by: N/A
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: 6/03/2025
Individual(s) responsible for follow up: Wanda Gautney, Purchasing Director
Action required (list contact persons/addresses if documents are to be mailed or emailed): Letter to Contractor
Additional instructions/notes: Admin - Append Change Order #1 to original Contract.