Agenda item title: County Road 11 (Greeno Road) Drainage Improvements - Permission to Advertise
Attachments: 1. Map

Meeting Type:   BCC Regular Meeting

Meeting Date:  2/6/2024

Item Status:   New

From: Frank Lundy, P.E., County Engineer
           Mark Acreman, P.E.
, Assistant County Engineer
           Seth Peterson, P.E.
, Pre-Construction Manager

Submitted by:  John Sedlack, Design Tech III

______________________________________________________________________

 

ITEM TITLE

Title

County Road 11 (Greeno Road) Drainage Improvements - Permission to Advertise

End

STAFF RECOMMENDATION

Recommendation

Take the following actions:

1) Approve the Purchasing Director to place a competitive bid for the County Road 11 (Greeno Road) Drainage Improvement Project; and

2) Approve the Chairman to execute any project related documents.

End

BACKGROUND INFORMATION

 

Background:  This project is located on County Road 11 (Greeno Road) in the Barnwell Community. Numerous flooding events have occurred over the years causing roadway failures, ditch erosion, loss of access to property and flooding of homes.

The proposed improvements include installing a closed drainage system and reinforcing the remaining open ditches with tied concrete block matting.

Previous Commission action/date:  N/A

 

FINANCIAL IMPACT

 

Total cost of recommendation:  Actual Cost to be determined once bids are opened.

 

Budget line item(s) to be used: 

HW23067-4CONTRCN-4CONTR SRV-4ADVERTISE

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up: 

Highway Design staff will submit advertisement to Wanda Gautney, Purchasing Director, when plans and contract documents are finalized. Purchasing Director will advertise project for competitive bid.

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  N/A

 

Additional instructions/notes:  N/A