Meeting Type: BCC Regular Meeting
Meeting Date: 11/5/2024
Item Status: New
From: Frank Lundy, P.E., County Engineer
Mark Acreman, P.E., Assistant County Engineer
Seth Peterson, P.E., Pre-Construction Manager
Submitted by: Lisa Sangster, Administrative Support Specialist IV
______________________________________________________________________
ITEM TITLE
Title
Fiscal Year 2025 Alabama Transportation Rehabilitation and Improvement Program II (ATRIP-II) - State Route 59 and County Road 32 Intersection Safety Improvements
End
STAFF RECOMMENDATION
Recommendation
Take the following actions:
1) Adopt Resolution #2025-026 which approves the Highway Department to prepare and submit an application for the Fiscal Year 2025 Alabama Transportation Rehabilitation and Improvement Program II (ATRIP-II) requesting federal funding for the addition of a turn lane and traffic signal upgrades at State Route 59 and County Road 32; and
2) Authorize the Chairman to execute a Letter of Intent to the Alabama Department of Transportation (ALDOT) advising of Baldwin County’s intent to apply for federal funds for construction of the project; and
3) Authorize the Chairman to sign any related documents.
End
BACKGROUND INFORMATION
Background: The FY 2025 ATRIP-II application deadline is November 15, 2024. The project sponsor can apply for up to $2,000,000.00 in non-matching requirement funds. Design, right-of-way, and construction are eligible for funding under the ATRIP-II Program.
Previous Commission action/date: N/A
FINANCIAL IMPACT
Total cost of recommendation: N/A
Budget line item(s) to be used: N/A
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
N/A
Reviewed/approved by: N/A
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: N/A
Individual(s) responsible for follow up: Administration Staff place letter of intent on Commission letterhead and have resolution and letter of Intent signed by Chairman. Return to Highway Department (Ashlie Rickard) for inclusion in project application package.
Action required (list contact persons/addresses if documents are to be mailed or emailed):
Contact:
Mr. Bradley L. Lindsey, P.E.
State Local Transportation Bureau Chief
Alabama Department of Transportation
1409 Coliseum Boulevard
Montgomery, Alabama 36130
Additional instructions/notes: Administration Staff upload resolution to BCAP.