Legislation Details

File #: 26-1017    Version: 1
Agenda section: Consent Status: Agenda Ready
File created: 7/27/2026 Meeting type: Baldwin County Commission Regular
On agenda: 8/4/2026 Final action:
Agenda item title: Extend County Road 20 from Hickory Street South to County Road 65 - Permission to Advertise
Attachments: 1. Map-CR20 from Hickory St S to CR65
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Meeting Type:   BCC Regular Meeting

Meeting Date:  8/4/2026

Item Status:   New

From: Frank Lundy, P.E., County Engineer
           Mark Acreman, P.E., Assistant County Engineer
           Seth Peterson, P.E., Pre-Construction Manager

Submitted by:  John Sedlack, Project Coordinator

______________________________________________________________________

 

ITEM TITLE

Title

Extend County Road 20 from Hickory Street South to County Road 65 - Permission to Advertise

End

STAFF RECOMMENDATION

Recommendation

Take the following actions:

 

1) Authorize the Purchasing Director to place a competitive bid to extend County Road 20 from Hickory Street South to County Road 65; and

 

2) Authorize the Chairman to execute any project-related documents.

 

End

BACKGROUND INFORMATION

 

Background: This project will support the Baldwin County Commission’s Strategic Plan Goals for Growth and Infrastructure Balance and Public Safety by improving and expanding the local road system. The project will provide 1 mile of new paved roadway, a 160-foot bridge, and intersection improvements on County Road 20 connecting County Road 65 to State Road 59 in Foley. This construction project is being funded through the U.S. Treasury RESTORE ACT. The estimated cost for advertising is $1,000.00.

 

Previous Commission action/date: 

October 19, 2021 - Approved a fee increase of $137,500.00 for additional design services performed by TTL, Inc., for the County Road 20 Extension from Hickory Street South to County Road 65.

 

March 2, 2021 - The Commission waived Baldwin County Commission Policy #9.10 - Engineering, Environmental Monitoring and Surveying Services and approved on-call consultant TTL, Inc., to perform design services for the County Road 20 Extension Project with design fees not to exceed $250,000.00.

 

September 22, 2020 - The Commission adopted Resolution #2020-127 approving the Fiscal Year 2021 Budget allocating $535,000.00 for Design and Right-of-Way for the County Road 20 Extension Project.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  N/A

 

Budget line item(s) to be used:  HW21101000.4CONTRCN .4CONTR SRV.4ADVERTISE

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow-up:   Highway Pre-Construction staff will submit advertisement to Wanda Gautney, Purchasing Director, when plans and contract documents are finalized. The Purchasing Director will advertise the project for competitive bid. 

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  N/A

 

Additional instructions/notes:  N/A