Legislation Details

File #: 26-0718    Version: 1
Agenda section: Consent Status: Agenda Ready
File created: 4/23/2026 Meeting type: Baldwin County Commission Regular
On agenda: 5/5/2026 Final action:
Agenda item title: Alabama Gulf Coast Recovery Council, State Expenditure Plan #11: Lillian Park Beach Habitat and Shoreline Protection - Subaward Grant Agreement - Amendment No. 4
Attachments: 1. Subaward Grant Agreement - Amendment No. 4 (REDACTED), 2. ADCNR - Disclosure Statement 4 (REDACTED)
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Meeting Type:   BCC Regular Meeting

Meeting Date:  5/5/2026

Item Status:   New

From: Frank Lundy, P.E., County Engineer
           Mark Acreman, P.E., Assistant County Engineer
           Seth Peterson, P.E., Pre-Construction Manager

Submitted by:  Stacy Appleton, Project Coordinator

______________________________________________________________________

 

ITEM TITLE

Title

Alabama Gulf Coast Recovery Council, State Expenditure Plan #11: Lillian Park Beach Habitat and Shoreline Protection - Subaward Grant Agreement - Amendment No. 4

End

STAFF RECOMMENDATION

Recommendation

Approve and authorize the Chairman to execute the Subaward Grant Agreement - Amendment No. 4 and Disclosure Statement between Alabama Department of Conservation and Natural Resources and Baldwin County Commission for the State Expenditure Plan #11: Lillian Park Beach Habitat and Shoreline Protection project which adds $60,001.00 in RESTORE funding to the project, corrects an administrative error in the total amount of Federal Funds obligated to Subrecipient, extends the period of performance to December 31, 2028, and revises the milestones accordingly.

 

End

BACKGROUND INFORMATION

 

Background:  In April 2020 Baldwin County was awarded funding under the Resources and Ecosystem Sustainability, Tourist Opportunities, and Revived Economics of the Gulf Coast States Act of 2012 (RESTORE ACT) Grant for the Lillian Park Beach Habitat and Shoreline Protection project.

 

Previous Commission action/date: 

September 3, 2024 - Approved the Subaward Grant Agreement - Amendment No. 3 and Disclosure Statement with ADCNR for the State Expenditure Plan #11: Lillian Park Beach Habitat and Shoreline Protection project which adds $364,997.00 in RESTORE funds to the project, extends the period of performance to April 30, 2026, and revises the project milestones accordingly.

 

June 20, 2023 - Approved a Subaward Grant Agreement - Amendment No. 2 and Disclosure Statement with ADCNR for the State Expenditure Plan #11: Lillian Park Beach Habitat and Shoreline Protection project which adds $1,450,154.00 in RESTORE funds to the project and revises the project milestones accordingly.

 

July 19, 2022 - Approved a Subaward Grant Agreement - Amendment No. 1 and Disclosure Statement with ADCNR for the State Expenditure Plan #11: Lillian Park Beach Habitat and Shoreline Protection project which extended the grant performance period by thirty (30) months to October 31, 2024, and revised the project milestones accordingly.

 

June 2, 2020 - Approved a Subaward Grant Agreement for State Expenditure Plan #11: Lillian Park Beach Habitat and Shoreline Protection; and authorized the Purchasing Department and Highway Department to develop a “Request for Qualifications” (RFQ) for a Coast Processes Study and place an advertisement for submissions.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $60,001.00

 

Budget line item(s) to be used:  HW16069000.FEDST.ADCNR.RESTORE

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up:  Administration Staff prepare correspondence (no envelope needed) and have agreement and disclosure statement executed by the Chairman and County Administrator. Return original correspondence and documents to Highway Department (Stacy Appleton) for submission to the ADCNR for final execution.

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Contact:

 

Alabama Department of Conservation and Natural Resources

ATTN: Christopher M. Blankenship, Commissioner

64 N. Union Street, Suite 468

Montgomery, Alabama 36130

 

cc: Dr. Amy Hunter, Deepwater Horizon Restoration Coordinator, Brian Underwood, Katrina Taylor, Lynda Demko

 

Additional instructions/notes:  Administration - Tickler; append amendment to original agreement approved June 2, 2020, and re-upload to Contract #7747.