Agenda item title: Construction of Phase II Baldwin County Sheriff's Office Renovations of Old Bay Minette Police Department Building
Attachments: 1. Certificate of Substantial Completion

Meeting Type:   BCC Regular Meeting

Meeting Date:  3/3/2026

Item Status:   New

From: Wanda Gautney, Purchasing Director; Sheriff Anthony Lowery; Patrick Addison, PH&J Architects

Submitted by:  Jeanette Brown, Assistant Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Construction of Phase II Baldwin County Sheriff’s Office Renovations of Old Bay Minette Police Department Building

End

STAFF RECOMMENDATION

Recommendation

Approve and authorize the Chairman to execute the Certificate of Substantial Completion on the Construction of Phase II Baldwin County Sheriff’s Office Renovations of the Old Bay Minette Police Department Building.

 

End

BACKGROUND INFORMATION

 

Background:  The Architect, Patrick Addison, with PH&J Architects, Inc., is submitting for Commission approval the Certificate of Substantial Completion on the Construction of Phase II Baldwin County Sheriff’s Office Renovations of the Old Bay Minette Police Department Building.  The contractor has several items on the punch list that will be completed prior to receiving final payment.

 

Previous Commission action/date: 

11/06/2025 meeting: 1)  Approved and authorized the Chairman to execute Change Order #2, for labor, material and equipment to add four (4) floor boxes in Training Assembly Room, in the amount of $15,791.78 with JNB Services, LLC; and 2) Approved and authorized the Chairman to execute Allowance Authorization #2, to replace rusted roof decking, in the amount of $18,522.00 with JNB Services, LLC.  Allowance cost will be paid from project contingency allowance that was included in the bid amount.

05/20/2025 meeting: 1)  Approved and authorized the Chairman to execute Change Order #1, for labor, material and equipment to replace four (4) existing HVAC rooftop units, in the amount of $155,331.50 with JNB Services, LLC; and 2) Approved and authorized the Chairman to execute Allowance Authorization #1, for electrical work required to replace the four (4) existing HVAC rooftop units, in the amount of $21,795.74 with JNB Services, LLC.  Allowance cost will be paid from project contingency allowance that was included in the bid amount.

12/17/2024 meeting: Awarded the bid for Construction of Phase II Baldwin County Sheriff’s Office Renovations of the Old Bay Minette Police Department building located in Bay Minette to the lowest bidder, JNB Services, LLC, in the bid amount of $3,445,522.00; Construction time: 270 calendar days; and authorized the Chairman to execute the Contract.

12/19/2023 meeting: Approved the design of Phase II Baldwin County Sheriff’s Office Renovations of the Old Bay Minette Police Department building located in Bay Minette in the estimated construction cost of $3,899,195.24 not including the cost of the security and camera equipment and authorized the Purchasing Director and Architect to bid the project.

04/04/2023 meeting: Approved the AIA Contract for architectural services with PH & J Architects, Inc., for the Phase II Sheriff’s Office Renovations to the old City of Bay Minette Police Building purchased from the City of Bay Minette in the amount of 6.5% of the construction cost.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  N/A

 

Budget line item(s) to be used:  N/A

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  03/03/2026

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Contractor

 

Additional instructions/notes:  N/A