Meeting Type: BCC Regular Meeting
Meeting Date: 3/18/2025
Item Status: New
From: Wanda Gautney, Purchasing Director; Mark Acreman, Assistant County Engineer; Seth Peterson, Pre-Construction Manager
Submitted by: Jeanette Brown, Assistant Purchasing Director
______________________________________________________________________
ITEM TITLE
Title
Project No. HW22026 - Sherman Road Drainage Improvements for the Baldwin County Commission
End
STAFF RECOMMENDATION
Recommendation
Approve Change Order #1 in the amount of $60,857.17 for Project No. HW22026 - Sherman Road Drainage Improvements with McElhenney Construction Co., LLC, and authorize the Chairman to execute the Change Order.
End
BACKGROUND INFORMATION
Background: The Highway Department is submitting for Commission approval Change Order #1 in the amount of $60,857.17 for Project No. HW22026 - Sherman Road Drainage Improvements. The change order includes details of increased plan quantities of various materials and will not increase the contract time.
See attached Summary of Previous ARPA Commission Action.
Previous Commission action/date:
07/16/2024 meeting: Awarded the bid for Project No. HW22026 - Sherman Road Drainage Improvements to the lowest bidder, McElhenney Construction Co., LLC, in the Bid Amount $1,294,544.19; Construction Time: 150 working days; and authorized the Chairman to execute the Contract.
03/19/2024 meeting: 1) Approved the allocation of American Rescue Plan Act (ARPA) funds in the amount of $2,000,000 for the cost of the Drainage Improvements along Sherman Road Project, to include the replacement of the existing 62-foot timber substructure bridge constructed in 1954 with a new 80-foot concrete bridge to mitigate flooding impacts and improve safety; and 2) Adopted Resolution #2024-081 of the Baldwin County Commission allocating up to $2,000,000 of the ARPA funds for the Drainage Improvements along Sherman Road Project.
03/05/2024 meeting: 1) Approved the Purchasing Director to place a competitive bid for the Sherman Road Drainage Improvement Project; and 2) Approved the Chairman to execute any project related documents.
FINANCIAL IMPACT
Total cost of recommendation: $60,857.17
Budget line item(s) to be used: HW22026.4CONTRCN .4CONTR SRV. 4CONTRACT
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
N/A
Reviewed/approved by: N/A
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: 03/18/2025
Individual(s) responsible for follow up: Wanda Gautney, Purchasing Director
Action required (list contact persons/addresses if documents are to be mailed or emailed): Letter to Contractor
Additional instructions/notes: N/A