Agenda item title: Resolution #2025-073 and Utility Agreement for County Road 64 Capacity Improvement Project
Attachments: 1. Utility Agreement and Resolution #2025-073 (REDACTED), 2. Map

Meeting Type:   BCC Regular Meeting

Meeting Date:  2/18/2025

Item Status:   New

From: Frank Lundy, P.E., County Engineer
           Mark Acreman, P.E., Assistant County Engineer
           Seth Peterson, P.E., Pre-Construction Manager

Submitted by:  John Sedlack, Project Coordinator

______________________________________________________________________

 

ITEM TITLE

Title

Resolution #2025-073 and Utility Agreement for County Road 64 Capacity Improvement Project

End

STAFF RECOMMENDATION

Recommendation

Adopt Resolution #2025-073 and approve the Utility Agreement between the Baldwin County Commission and the Alabama Department of Transportation for utility relocation for widening, resurfacing and intersection improvements on County Road 64 from State Road 181 to Montelucia Way using 80% Federal funds and 20% County matching funds. (This Agreement shall be effective upon full execution and shall be in effect until the utility relocation project and reimbursements are completed.)

End

BACKGROUND INFORMATION

 

Background: The estimated cost for utility relocation on County Road 64 from State Road 181 to Montelucia Way is $1,995,210.00. The Eastern Shore Metropolitan Planning Organization (MPO) approved an allocation of $1,596,168.00 (80%) and the County will provide the local match of $399,042.00 (20%).

 

Previous Commission action/date: 

April 5, 2022 - The Commission adopted Resolution #2022-067 and approved a funding agreement between the Baldwin County Commission and the Alabama Department of Transportation (ALDOT) for right-of-way acquisition for the widening, resurfacing and intersection improvements on County Road 64 from State Road 181 to Montelucia Way using 80% Federal funds and 20% County matching funds.

 

October 1, 2019 - The Commission approved Resolution #2020-011 and submitted a Letter of Intent to use Federal Funds for the County Road 64 Capacity Improvement Project to ALDOT as part of the project initiation process.

 

July 16, 2019 - The Commission waived Baldwin County Commission Policy #9.10 - Engineering and Surveying Services and approved on-call consultant Volkert, Inc. to perform design services for the County Road 64 Capacity Improvements Project, with design fees not to exceed $526,142.00. The Eastern Shore Metropolitan Planning Organization (ESMPO) will fund 80% of the design fees and the County will provide the 20% local match.

 

April 16, 2019 - The Commission approved Resolution #2019-059 and a funding agreement between the Baldwin County Commission and ALDOT for the Preliminary Engineering to 3-Lane County Road 64 from State Route 181 to County Road 54 East and install a Roundabout at the Rigsby Road Intersection using 80% Federal funds and 20% County matching funds.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $399,042.00

 

Budget line item(s) to be used:  HW18068000-4CONTRCN-4CONTR SRV-4CONT111

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

No

 

Reviewed/approved by:  N/A

 

Additional comments:  Standard ALDOT Agreement.

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A.

 

Individual(s) responsible for follow up:  Administration Staff prepare correspondence and have the Chairman execute the Resolution and Agreement. Return to Highway Department (John Sedlack) for submittal to ALDOT.

 

Action required (list contact persons/addresses if documents are to be mailed or emailed): 

Contact: (No envelope needed)


Alabama Department of Transportation

ATTN: Matthew J. Ericksen, P.E.,

Southwest Region Engineer

1701 W. Interstate 65 Service Road North

Mobile, Alabama 36618

 

Additional instructions/notes:  Administration-Place in tickler for receipt of fully executed Agreement. Upload Agreement to Contracts with John Sedlack as originator. Set reminder date for one year from date of full execution.