Legislation Details

File #: 27-0116    Version: 1
Agenda section: Consent Status: Agenda Ready
File created: 10/8/2026 Meeting type: Baldwin County Commission Regular
On agenda: 10/20/2026 Final action:
Agenda item title: Change Orders Relating to Contract for Engineering / Environmental Services for County Road 13 and Corte Road Intersection Improvement Project for the Baldwin County Commission
Attachments: 1. CR13 at Corte Rd Proposal for Traffic Control Plan, 2. CR13 at Corte Rd Proposal for Glover Lane
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Meeting Type:   BCC Regular Meeting

Meeting Date:  10/20/2026

Item Status:   New

From: Wanda Gautney, Purchasing Director; Mark Acreman, Assistant County Engineer; Seth Peterson, Pre-Construction Manager

Submitted by:  Jeanette Brown, Assistant Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Change Orders Relating to Contract for Engineering / Environmental Services for County Road 13 and Corte Road Intersection Improvement Project for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Approve two (2) Change Orders in the total amount of $22,700.00 with Gresham Smith for additional Engineering / Environmental Services for the County Road 13 and Corte Road Intersection Improvement Project per the Scope and Fee Proposals.

 

End

BACKGROUND INFORMATION

 

Background:  Highway Staff is submitting two (2) Change Orders relating to the contract with Gresham Smith in the total amount of $22,700.00 for Commission approval. The Change Orders are for additional Engineering / Environmental Services for County Road 13 and Corte Road Intersection Improvement Project. One change order is for revisions to the traffic control plan to continue flow during construction in the amount of $12,900.00 and the other change order is to extend and widen Glover Lane in the amount of $9,800.00.

 

The original contract cost of $204,218.00 will be increased by these change orders in the amount of $22,700.00 to the new contract cost of $226,918.00.

 

Previous Commission action/date: 

04/01/2025 meeting:  Approved and authorized the Chairman to execute the Contract with Gresham Smith for the Engineering / Environmental Services for the County Road 13 and Corte Road Intersection Improvement Project in the estimated amount of $204,218.00.

 

12/17/2024 meeting:  Authorized staff to begin negotiations with Gresham Smith so that a final recommendation for award can be made to the Baldwin County Commission for the Engineering / Environmental Services for the County Road 13 and Corte Road Intersection Improvement Project.

 

10/15/2024 meeting:  Authorized the Purchasing Director to place advertisements for Fiscal Year 2025 Request for Qualifications (RFQ) for Engineering Services for the Highway Projects listed below:

 

Project No. HW19119 - Mannich Lane between Lipscomb Road and CR-9

Project No. HW25008 - CR-13 at Corte Road Roundabout

Project No. HW25006 - CR-65 Ext., CR-36 to CR-48 Section

Project No. HW25074 - Bridge Design on Styx River Road

Project No. HW21100000 - Pleasant Road Ext., SR-181 to Larry Street Road

Project No. HW23074 - Bruhn Road, CR-87 to Breman Road

09/17/2024 meeting:  Adopted the Baldwin County Fiscal Year 2024-2025 Budget (Resolution #2024-158) and Resolution #2024-159).

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $22,700.00

 

Budget line item(s) to be used:  HW25008.1PRECN.1CONTR SRV.1CONT111

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  10/20/2026

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Vendor

 

Additional instructions/notes:  Admin - append to Contract #8499