Agenda item title: Widening and Intersection Improvements on County Road 64 from State Road 181 to Montelucia Way - Non-Reimbursable Utility Agreements
Attachments: 1. AT&T - Non-Reimbursable Utility Agreement, 2. C-Spire - Non-Reimbursable Utility Agreement, 3. Uniti Fiber - Non-Reimbursable Utility Agreement, 4. Map - CR 64 from SR 181 to Montelucia Way

Meeting Type:   BCC Regular Meeting

Meeting Date:  8/19/2025

Item Status:   New

From: Frank Lundy, P.E., County Engineer
           Mark Acreman, P.E., Assistant County Engineer
           Seth Peterson, P.E., Pre-Construction Manager

Submitted by:  John Sedlack, Project Coordinator

______________________________________________________________________

 

ITEM TITLE

Title

Widening and Intersection Improvements on County Road 64 from State Road 181 to Montelucia Way - Non-Reimbursable Utility Agreements

End

STAFF RECOMMENDATION

Recommendation

Approve a Non-Reimbursable Utility Agreement with each of the following companies for the relocation of utilities to complete the widening and intersection improvements on County Road 64 from State Road 181 to Montelucia Way at no cost to the project:


AT&T
C-Spire
Uniti Fiber

The agreements shall be effective upon full execution and will terminate upon completion of the project.

 

End

BACKGROUND INFORMATION

 

Background:  The County Road 64 Widening Capacity Project has multiple utility conflicts along the entire corridor. The non-reimbursable utility agreements with AT&T, Uniti Fiber and C-Spire will outline the terms for relocations.

 

Previous Commission action/date: 

February 18, 2025 - The Commission adopted Resolution #2025-073 and approved the Utility Agreement between the Baldwin County Commission and the Alabama Department of Transportation for utility relocation for widening, resurfacing and intersection improvements on County Road 64 from State Road 181 to Montelucia Way using 80% Federal funds and 20% County matching funds.

 

January 21, 2025 - The Commission approved the Purchasing Director to place a competitive bid for the County Road 64 Clearing and Grubbing Project; and approved the Chairman to execute any project related documents.

 

April 5, 2022 - The Commission approved Resolution #2022-067 and a funding agreement between the Baldwin County Commission and the Alabama Department of Transportation for right-of-way acquisition for the widening, resurfacing and intersection improvements on County Road 64 from State Road 181 to Montelucia Way using 80% Federal funds and 20% County matching funds.

 

October 1, 2019 - The Commission approved Resolution #2020-011 and submitting a Letter of Intent to use Federal Funds for the County Road 64 Capacity Improvement Project to the Alabama Department of Transportation (ALDOT) as part of the project initiation process.

 

July 16, 2019 - The Commission waived Baldwin County Commission Policy #9.10 - Engineering and Surveying Services and approved on-call consultant Volkert, Inc. to perform design services for the County Road 64 Capacity Improvements Project, with design fees not to exceed $526,142.00. The Eastern Shore Metropolitan Planning Organization (ESMPO) will fund 80% of the design fees and the County will provide the 20% local match.

 

April 16, 2019 - The Commission approved Resolution #2019-059 and a funding agreement between the Baldwin County Commission and the Alabama Department of Transportation for the Preliminary Engineering to 3-Lane County Road 64 from State Route 181 to County Road 54 East and install a Roundabout.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  N/A

 

Budget line item(s) to be used:  N/A

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

No

 

Reviewed/approved by:  N/A

 

Additional comments:  Standard ALDOT Agreement used.

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up:  Administration Staff prepare correspondence and have the Chairman sign agreements. Return correspondence and signed agreements to Highway Department (John Sedlack) for forwarding to ALDOT for final execution.

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Contact:

 

Alabama Department of Transportation

ATTN: Stephanie Dragotta, P.E.

Local Transportation Engineer - Mobile

1701 I-65 Service Road North

Mobile, Alabama 36618

 

Additional instructions/notes:  Administration - tickler; once agreements are received back fully executed, upload to Contracts with John Sedlack as originator.