Agenda item title: Right-of-Way Acquisition for Intersection Safety Improvements
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Meeting Type:   BCC Regular Meeting

Meeting Date:  11/18/2025

Item Status:   New

From: Frank Lundy, P.E., County Engineer
           Mark Acreman, P.E., Assistant County Engineer

Submitted by:  Lisa Sangster, Administrative Support Coordinator

______________________________________________________________________

 

ITEM TITLE

Title

Right-of-Way Acquisition for Intersection Safety Improvements

End

STAFF RECOMMENDATION

Recommendation

Authorize the Highway Department to acquire right-of-way for future intersection safety improvements along State Route 287 between Old Jack Springs Road and Willie Cooper Road.

End

BACKGROUND INFORMATION

 

Background:  The County Commission previously authorized intersection safety improvement projects along State Route 287 in relation to the opening of the Novelis Plant. Given the increase in traffic volume and demand along State Route 287, additional intersection safety improvements are warranted.

 

Previous Commission action/date:  N/A

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $300,000.00 Estimate

 

Budget line item(s) to be used:  TIF District Funds

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up:  Highway Department staff will begin process for purchase of right-of-way for future intersection safety improvement projects.

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  N/A

 

Additional instructions/notes:  N/A