File #: 25-0850    Version: 1
Agenda section: Consent Status: Passed
File created: 5/23/2025 Meeting type: Baldwin County Commission Regular
On agenda: 6/3/2025 Final action: 6/3/2025
Agenda item title: Project No. HW21125000 Culvert Installation on Paul Cleverdon Road over East Tributary to Baker Branch for the Baldwin County Commission
Attachments: 1. Change Order No. 2-Project No. HW21125000

Meeting Type:   BCC Regular Meeting

Meeting Date:  6/3/2025

Item Status:   New

From: Wanda Gautney, Purchasing Director; Mark Acreman, Assistant County Engineer; Tucker Stuart, Operations Manager, Josh Bell, Construction Engineer

Submitted by:  Wanda Gautney, Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Project No. HW21125000 Culvert Installation on Paul Cleverdon Road over East Tributary to Baker Branch for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Approve Change Order #2 in the amount of $5,454.05 with Blade Construction, LLC, for HW21125000 Culvert Installation on Paul Cleverdon Road over East Tributary to Baker Branch and authorize the Chairman to execute the Change Order. (Change Order #2 does not increase the construction cost of the project).

 

End

BACKGROUND INFORMATION

 

Background:  The Highway Department is submitting to the Commission for approval Change Order #2 in the amount of $5,454.05 for Project HW21125000 Culvert Replacement on Paul Cleverdon Rd over East Tributary to Baker Branch. This Change Order is shifting pay item quantities from project HW21093 Culvert replacement on County Road 34S over East Tributary to Baker Branch to project HW21125 Culvert replacement on Paul Cleverdon Road over East Tributary to Baker Branch. These pay items were required to be shifted between projects due to the sequence of construction needed for the work to be performed. 

 

Change Order #2 does not increase the construction cost of these projects.

 

Original construction cost was $1,720,561.60 including Change Order #1 ($71,252.82) and #2 (no increase) the final construction cost is $1,791,814.42.

 

Previous Commission action/date: 

09/17/2024 meeting: Approved Change Order #1 in the amount of $71,252.82 with Blade Construction, LLC, for Project No. HW21092000 Culvert Replacement on Davis Road over Baker Branch and authorized the Chairman to execute the Change Order.

 

03/07/2023 meeting: Awarded the bid for Project No. HW21092000 Culvert Replacement on Davis Road over Baker Branch - Project No. HW21093000 Culvert Replacement on County Road 34S over East Tributary to Baker Branch - HW21094000 Culvert Replacement on County Road 34S over West Tributary to Baker Branch - Project No. HW21125000 Culvert Installation on Paul Cleverdon Road over East Tributary to Baker Branch to the lowest bidder, Blade Construction, LLC, in the Bid Amount $1,720,561.60; Construction Time: 195 working days; and authorized the Chairman to execute the Contract.

 

09/07/2021 meeting: Authorized the Purchasing Director to place a competitive bid for the following bridge replacement projects once plans and contract documents are complete:  1) Project No. HW21092000 - Davis Road over Baker Branch; 2) Project No. HW21093000 - County Road 34S Road over East Tributary to Baker Branch; 3) Project No. HW21094000 - County Road 34S over West Tributary to Baker Branch; 4) Project No. HW21125000 - Paul Cleverdon Road over East Tributary to Baker Branch.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  No Increase in Construction Cost

 

Budget line item(s) to be used:  Moving $5,454.05 from HW21093 to HW21125-4CONTRCN-4CONTR SRV-4CONTRACT

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  6/03/2025

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Revise Purchase Order so Retainage can be paid.

 

Additional instructions/notes:  Admin-Append Change Order #2 to original Contract. Contract remains inactive.