Meeting Type: BCC Regular Meeting
Meeting Date: 7/16/2025
Item Status: New
From: Frank Lundy, P.E., County Engineer
Mark Acreman, P.E., Assistant County Engineer
Lynda Demko, Chief Accountant
Submitted by: Lisa Sangster, Administrative Support Specialist IV
______________________________________________________________________
ITEM TITLE
Title
Rebuild Alabama - Baldwin County Fiscal Year 2025 Contractor Report
End
STAFF RECOMMENDATION
Recommendation
Approve the Chairman to execute the Fiscal Year 2025 County Rebuild Alabama Contractor Report for awarded projects funded with County Rebuild Alabama Funds.
End
BACKGROUND INFORMATION
Background: Governor Kay Ivey signed the Rebuild Alabama Act #2019-2 into law on March 12, 2019. This Act amends the Code of Alabama 1975 and will be used for transportation infrastructure improvement and preservation and maintenance projects pursuant to the provisions of the Act. The Alabama State Act levies an additional 10¢ excise tax on gasoline and diesel fuel implemented over a three-year period.
Counties shall adopt an annual County Transportation Plan (CTP) no later than August 31st for the next fiscal year.
The County Rebuild Alabama Contractor Report provides a detailed report of all contractors awarded projects funded with County Rebuild Alabama Funds. This report is due annually on October 1st.
Previous Commission action/date:
August 20, 2024 - The Commission adopted the Rebuild Alabama - Baldwin County FY 25 County Transportation Plan which included the following projects:
County Road 87 - Resurface from Channel 44 Road to County Road 12
County Road 73 - Resurface from Foley Beach Express to County Road 36
County Road 99 - Resurface from County Road 91 to Carrier Drive
Scenic Highway 98 - Bridge Replacement over Point Clear Creek; and approved the display of the County Transportation Plan in conspicuous places at the Baldwin County Courthouses, Baldwin County Commission offices, Baldwin County Highway Department, Baldwin County website and other places deemed appropriate by the Baldwin County Commission.
FINANCIAL IMPACT
Total cost of recommendation: N/A
Budget line item(s) to be used: N/A
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
N/A
Reviewed/approved by: N/A
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: N/A
Individual(s) responsible for follow up: Administration Staff have the County Rebuild Alabama Contractor Report signed by the Chairman and return to the Highway Department (Lisa Sangster) for submission to the Association of County Commissions of Alabama.
Action required (list contact persons/addresses if documents are to be mailed or emailed): N/A
Additional instructions/notes: N/A