Agenda item title: Group 5 of ERPR-9072 - Permanent Repair for Various Sites Due to Severe Weather Event Beginning September 16, 2020, FHWA Disaster #AL20-2 for the Baldwin County Commission
Attachments: 1. Change Order #1 HW22167-ERPR-9072(974), 2. Change Order #1 HW22168-ERPR-9072(967)

Meeting Type:   BCC Regular Meeting

Meeting Date:  11/5/2024

Item Status:   New

From: Wanda Gautney, Purchasing Director; Mark Acreman, Assistant County Engineer; Seth Peterson, Pre-Construction Manager

Submitted by:  Jeanette Brown, Assistant Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Group 5 of ERPR-9072 - Permanent Repair for Various Sites Due to Severe Weather Event Beginning September 16, 2020, FHWA Disaster #AL20-2 for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Approve Change Orders #1 for Group 5 of the ERPR-9072 in the amount of $21,452.98 for Project No. HW22167 and $3,785.32 for Project No. HW22168 in the total amount of $25,238.30 with Arrington Curb & Excavation, Inc., and authorize the Chairman to execute the Change Orders.

End

BACKGROUND INFORMATION

 

Background:  The Highway Department is submitting for Commission approval Change Orders #1 in the amount of $21,452.98 for Project No. HW22167 - ERPR-9072(974) CR 112 - 4,138 ft East of Barrineau Park Road and $3,785.32 for Project No. HW22168 - ERPR-9072(967) CR 112 - 2,223 ft West of Barrineau Park Road for a total amount of $25,238.30.

 

Both projects are part of Group 5 of the ERPR-9072 and had a few overruns over planned quantities as follows:

 

1) Additional length of roadway was required to be removed to place the pipes at a skewed angle per the plans. Subsequently, additional borrow materials, crushed aggregates, bituminous pavements, and pavement markings were required; and

 

2) Additional topsoil, solid sodding and riprap was needed to stabilize slopes due to inadequate field conditions.

 

Previous Commission action/date: 

05/07/2024 meeting: Awarded the bid for Group 5 of the ERPR-9072 - Permanent Repair for Various Sites Due to a Severe Weather Event Beginning on September 16, 2020, FHWA Disaster #AL20-2 to the lowest responsible bidder, Arrington Curb & Excavation, Inc., Bid Amount $1,144,178.74; Construction Time: 125 working days; and authorized the Chairman to execute the Contract.

 

07/19/2022 meeting: 1) Approved the Federal Highway (FHWA) Emergency Repair (ER) Projects for Hurricane Sally emergency/permanent repairs, adopted the following resolutions and approved the corresponding Preliminary Engineering and Construction Funding Agreements between Alabama Department of Transportation (ALDOT) and the Baldwin County Commission:

 

1) Resolution #2022-116 - HW22160/County Road 55 (4090 ft S of County Rd 48)

2) Resolution #2022-117 - HW22156/Underwood Road (489 ft E of George Younce Rd)

3) Resolution #2022-118 - HW22159/County Road 55 (1218 ft N of County Rd 32)

4) Resolution #2022-119 - HW22162/County Road 33 (1277 ft S of Clay City Rd)

5) Resolution #2022-120 - HW22161/County Road 52 (1540 ft E of Hill Rd)

6) Resolution #2022-121 - HW22164/County Road 9 (787 ft S of Woodhaven Dairy Rd W)

7) Resolution #2022-122 - HW22158/County Road 55 (293 ft S of Lakeway Dr)

8) Resolution #2022-123 - HW22163/County Road 10 (335 ft E of Cook Rd)

9) Resolution #2022-124 - HW22157/County Road 65 (1027 ft S of County Rd 16)

10) Resolution #2022-125 - HW21174/County Road 32 (2349 ft W of County Rd 95)

11) Resolution #2022-126 - HW22173/County Road 32 (1085 ft E of County Rd 87)

12) Resolution #2022-127 - HW22172/County Road 32 (2680 ft E of County Rd 83)

13) Resolution #2022-128 - HW22171/County Road 83 (990 ft S of Woerner Rd)

14) Resolution #2022-129 - HW22170/County Road 87 (765 ft N of Seed Orchard Rd)

15) Resolution #2022-130 - HW22169/County Road 87 (2140 ft S of Seed Orchard Rd)

16) Resolution #2022-131 - HW22168/County Road 112 (2223 ft W of Barrineau Park Rd)

17) Resolution #2022-132 - HW22167/County Road 112 (4138 ft E of Barrineau Park Rd)

18) Resolution #2022-133 - HW22166/County Road 20 (Miflin Rd) (410 ft E of Swift Church Rd)

19) Resolution #2022-134 - HW22165/NW 1st Street (2433 ft S of County Rd 36)

20) Resolution #2022-135 - TBD/Bald 01 Signage (Various locations)

21) Resolution #2022-136 - TBD/Bald 02 Signage (Various locations)

22) Resolution #2022-137 - TBD/County Road 48 (353 ft E of Langford Rd)

 

The agreements shall be effective upon full execution and shall remain in effect until the project has been completed and reimbursement is complete. The agreements may be terminated by either party upon the delivery of a thirty (30) day notice of termination; and

 

2) Approved and authorized the Purchasing Director to place a competitive bid for each project once final plans and contracts are completed.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $25,238.30

 

Budget line item(s) to be used: 

$21,452.98 HW22167 4CONTRCN .4CONTR SRV. 4CONTRACT

$3,785.32 HW22168 4CONTRCN .4CONTR SRV. 4CONTRACT

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  11/05/2024

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Vendor

 

Additional instructions/notes:  N/A