File #: 24-1126    Version: 1
Agenda section: Consent Status: Agenda Ready
File created: 9/6/2024 Meeting type: Baldwin County Commission Regular
On agenda: 9/17/2024 Final action: 9/17/2024
Agenda item title: Project No. HW23087 - Drainage Improvements Main Street South of Forest Park Drive, Montrose District, for the Baldwin County Commission
Attachments: 1. Change Order #1 Main Street, 2. Summary of Previous ARPA Commission Action

Meeting Type:   BCC Regular Meeting

Meeting Date:  9/17/2024

Item Status:   New

From: Wanda Gautney, Purchasing Director; Mark Acreman, Assistant County Engineer; Tucker Stuart, Construction Engineer

Submitted by:  Wanda Gautney, Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Project No. HW23087 - Drainage Improvements Main Street South of Forest Park Drive, Montrose District, for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Approve Change Order #1 in the amount of $18,367.42 with McElhenney Construction Co., LLC, for Project No. HW23087 - Improvements Main Street South of Forest Park Drive, Montrose District, and authorize the Chairman to execute the Change Order.

End

BACKGROUND INFORMATION

 

Background:  The Highway Department is submitting for Commission approval Change Order #1 in the amount of $18,367.42 for Project No. HW23087 - Main Street (Scenic 98) Drainage Improvements. The project had a few overruns over planned quantities. 1) Additional Sidewalk had to be replaced due to cracking and noncompliance with ADA Standards. 2) Additional topsoil, solid sodding and riprap was needed to stabilize slopes due to unplanned utility relocations 3) Additional traffic control items were warranted over planned quantities to ensure adequate safety of traveling public. Funding will be from the American Rescue Plan Act (ARPA) funds.

 

See attached Summary of Previous ARPA Commission Action.

 

Previous Commission action/date: 

06/04/2024 meeting: Awarded the bid for Project No. HW23087 - Drainage Improvements Main Street South of Forest Park Drive, Montrose District to the lowest bidder, McElhenney Construction Co., LLC, in the Bid Amount $185,588.02; Construction Time: 30 working days; and authorized the Chairman to execute the Contract.

 

02/20/2024 meeting:  1) Approved the allocation of “real” ARPA funds in the amount of $200,000.00 for the cost of the Drainage Improvements along Main Street Project, to include the improvements to the existing stormwater system to mitigate flooding impacts and improve safety; and 2) Adopted Resolution #2024-043 of the Baldwin County Commission allocating up to $200,000.00 of the ARPA funds for the Drainage Improvements along Main Street Project and; 3) Approved the Chairman to execute any project related documents.

 

2/06/2024 meeting:  1) Approved the Purchasing Director to place a competitive bid for the Main Street Drainage Improvement Project; and 2) Approved the Chairman to execute any project related documents.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $18,367.42

 

Budget line item(s) to be used:  HW23087.4CONTRCN .4CONTR SRV. 4CONTRACT

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  9/17/2024

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Contractor

 

Additional instructions/notes:  N/A