Agenda item title: Project No. HW24084 - Construction of Mega Site Novelis Rail Spur for the Baldwin County Commission
Attachments: 1. Change Order #1

Meeting Type:   BCC Regular Meeting

Meeting Date:  10/15/2024

Item Status:   New

From: Wanda Gautney, Purchasing Director; Mark Acreman, Assistant County Engineer; Seth Peterson, Pre-Construction Manager

Submitted by:  Jeanette Brown, Assistant Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Project No. HW24084 - Construction of Mega Site Novelis Rail Spur for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Approve Change Order #1 in the amount of $169,708.50 with S. A. Graham Co., Inc., for Project No. HW24084 - Construction of Mega Site Novelis Rail Spur and authorize the Chairman to execute the Change Order.

End

BACKGROUND INFORMATION

 

Background:  The Highway Department is submitting for Commission approval Change Order #1 in the amount of $169,708.50 with S. A. Graham Co., Inc., for Project No. HW24084 - Construction of the Mega Site Novelis Rail Spur. Due to excessive groundwater issues encountered within the project on the east slope of rail spur, 1,700 LF of 6” Underdrain Piping is required to move this water to the plan grades of ditches. Additionally, CSX is requiring the removal of 300 LF of existing non-insulated steel ties be replaced with 7’ x 9” x 8’-6” wood ties from the connection point of the rail spur to CSX mainline. The switch gear installed on CSX mainline track requires nonconductive rail ties for 300 LF from connection points.

 

Previous Commission action/date: 

06/18/2024 meeting:  Awarded the bid for Project No. HW24084 - Construction of Mega Site Novelis Rail Spur to the lowest bidder, S. A. Graham Co., Inc., in the Bid Amount $14,869,642.87; Construction Time: 540 calendar days; and authorized the Chairman to execute the Contract.

02/20/2024 meeting:  1) Approved the Purchasing Director to place a competitive bid for the construction of the Novelis Manufacturing Facility - North Railroad and Bridge project; and 2) Approved the Chairman to execute any project related documents.

09/09/2022 meeting:  Approved waiving Baldwin County Policy #9.10 - Engineering, Environmental Monitoring and Surveying Services and approved on-call consultant Volkert to perform engineering services for the South Alabama Mega Site Development Project with fees not to exceed $4,232,020.00.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $169,708.50

 

Budget line item(s) to be used:  HW24084. 4CONTRCN .4CONTR SRV. 4CONTRACT

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  10/15/2024

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Contractor

 