Legislation Details

File #: 24-0708    Version: 1
Agenda section: Consent Status: Agenda Ready
File created: 4/18/2024 Meeting type: Baldwin County Commission Regular
On agenda: 5/7/2024 Final action: 5/7/2024
Agenda item title: Live Oak Landing Boat Launch Repairs for the Baldwin County Commission
Attachments: 1. Change Order #1

Meeting Type:   BCC Regular Meeting

Meeting Date:  5/7/2024

Item Status:   New

From: Wanda Gautney, Purchasing Director / Frank Lundy, County Engineer / Madison Steele, Horticulturist / Steve Delahunty, Engineer/Sawgrass Consulting, LLC

Submitted by:  Wanda Gautney, Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Live Oak Landing Boat Launch Repairs for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Approve Change Order #1 in the amount of $39,700.00 with Gillis Construction, Inc., on the Live Oak Landing Boat Launch project and authorize the Chairman to execute the Change Order.

End

BACKGROUND INFORMATION

 

Background:  The Engineer, Steve Delahunty, with Sawgrass Construction, LLC, is submitting for Commission approval Change Order #1 in the amount of $39,700.00 for the Live Oak Landing Boat Launch project.  The Engineer and County staff discovered during final inspection of the boat launch project that this year’s high water caused damage to the north and south floating docks and some of the pilings on the docks.  The north and south floating dock systems and decking exceed the maximum ADA cross slope (2%) during low tide conditions. The additional work will increase the original construction time by 15 working days.  The recommended improvements are in the immediate best interest of Public Safety for those that use this facility and mitigation of future repair cost to the County.

 

The original construction cost was $272,660.00; including Change Order #1 in the amount of $39,700.00, the new construction cost will be $312,360.00 with an increase in construction time of 15 working days.

 

The Commission budgeted $315,000.00 to repair the three Live Oak Boat Launches during the FY23 budget.

 

Previous Commission action/date: 

09/05/2023 meeting: 1) Awarded the bid to Gillis Construction, Inc., in the bid amount of $272,660.00; Construction Time: 35 working days; and authorized the Chairman to execute the Contract; and 2) Not awarding Alternate #1 (Temporary Steel Sheet Piling) $110,250.00.

 

06/06/2023 meeting:  1) Authorized the Purchasing Director and Engineer to place a competitive bid and authorized the Chairman/Purchasing Division Commissioner for the Baldwin County Commission to approve any necessary addendums or clarifications if required after the bid is advertised; and 2) Approved the Chairman to execute any project related documents.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $39,700.00

 

Budget line item(s) to be used:  14457238.55240

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

Review of Change Order No. 1

 

Reviewed/approved by:  Brad Hicks, County Engineer

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  05/07/2024

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Contractor

 

Additional instructions/notes:  N/A