Meeting Type: BCC Work Session
Meeting Date: 4/9/2019
Item Status: New
From: Wanda Gautney, Purchasing Director/Joey Nunnally, County Engineer/Frank Lundy, Maintenance Engineer
Submitted by: Wanda Gautney, Purchasing Director
______________________________________________________________________
ITEM TITLE
Title
Competitive Bid #WG19-30 - Purchase and Installation of Four (4) Metal Buildings at Various Baldwin County Highway Facility Locations for the Baldwin County Commission
Body
STAFF RECOMMENDATION
Recommendation
Award Bid #WG19-30 - Purchase and Installation of Four (4) Metal Buildings at Various Baldwin County Highway Facility Locations to the lowest bidder, Sun Coast Builders, Inc., in the amount of $179,677.00; Completion Time: 12 weeks, and authorize the Chairman to execute the Contract.
End
BACKGROUND INFORMATION
Previous Commission action/date:
03/06/19 meeting: 1) Approved the specifications and authorized the Purchasing Director to place a competitive bid for the purchase and installation of four (4) metal buildings at various Baldwin County Highway Facility locations; and 2) Further, authorized the Chairman/Purchasing Division Commissioner for the Baldwin County Commission to approve any necessary addendums or clarifications if required
after the bid is advertised.
04/02/19 meeting: Made Addendum No. 1 which includes three (3) changes and several clarifications to the bid specifications for the Purchase and Installation of Four (4) Metal Buildings at Various Baldwin County Highway Facility Locations, part of the April 2, 2019, official record of the Baldwin County Commission.
Background: Bids opened in the Purchasing Conference Room on April 1, 2019 at 1:30 P.M. Two (2) bids were received. The lowest bid was received from Sun Coast Builders, Inc., in the amount of $179,677.00. They had one (1) exception to the bid specifications. They did not include a copy of their current insurance certificate as stated in the specifications with their bid response. Staff is of the opinion that the exception is minor since the County has a copy of Sun Coast Builders current insurance certificate on file and is requesting that the Commission award the bid to the lowest bidder, Sun Coast Builders, Inc., in the amount of $179,677.00 with a completion time of 12 weeks. Bid Tabulation attached for review.
Eighty-six (86) Vendors registered on the County website and were notified by email as well as sent a postcard, via U.S. Postal Service notifying them of this solicitation. Five (5) Vendors attended the mandatory Pre-Bid Meeting.
FINANCIAL IMPACT
Total cost of recommendation: $179,677.00
Budget line item(s) to be used: 53112.5500
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
Standard County Contract
Reviewed/approved by: David Conner
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: 04/16/2019
Individual(s) responsible for follow up: Wanda Gautney/Purchasing Director
Action required (list contact persons/addresses if documents are to be mailed or emailed): Letter to Bidders