Meeting Type: BCC Regular Meeting
Meeting Date: 11/19/2019
Item Status: New
From: Joey Nunnally, P.E., County Engineer
Submitted by: John Sedlack, Design Tech III
______________________________________________________________________
ITEM TITLE
Title
Resolution No. 2020-026 and Preliminary Engineering Funding Agreement for the Addition of Paved Shoulders on County Road 99 from Carrier Drive to Spanish Cove Drive
Body
STAFF RECOMMENDATION
Recommendation
Approve Resolution No. 2020-026 and an agreement with the Alabama Department of Transportation (ALDOT) for the financing of Preliminary Engineering costs associated with the addition of paved shoulders on County Road 99 from Carrier Drive to Spanish Cove Drive. The estimated cost for Preliminary Engineering is $50,000.00 with $40,000.00 (80%) coming from the Florida - Alabama Transportation Planning Organization and Baldwin County funding the remaining $10,000.00 (20%). Funding is subject to availability of Federal Aid Funds at the time of authorization. (Agreement shall be effective on the date of the approval of the Governor of Alabama and may be terminated by either party upon the delivery of a thirty (30) day notice of termination.)
End
BACKGROUND INFORMATION
Previous Commission action/date: N/A
Background:
The Florida - Alabama Transportation Organization has allocated funding for shoulder widening on County Road 99 in the Lillian Community. This agreement and resolution covers the Preliminary Engineering phase of the project. The Construction phase will be allocated in future fiscal year funding.
FINANCIAL IMPACT
Total cost of recommendation: $10,000.00 estimated cost
Budget line item(s) to be used: 0222319.5165
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
Yes
Reviewed/approved by: Brad Hicks, County Attorney (Approved 11/8/2019) los
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: N/A
Individual(s) responsible for follow up: Commission Staff have Resolution and Agreement fully executed by Commission; Return to Hwy Department (John Sedlack). Highway Department will submit Agreement and Resolution to ALDOT.
Action required (list contact persons/addresses if documents are to be mailed or emailed):
Mail Correspondence contact:
Thomas W. Goodman, Jr., P.E.
Local Transportation Engineer-Mobile
ALDOT, Southwest Region
1701 W I-65 Service Rd North
Mobile, Alabama 36618