Agenda item title: Rescinding and Approving Supplemental Reimbursable Utility Agreement - County Road 13 at County Road 44 Roundabout
Attachments: 1. Riviera Utilities - Supplemental Reimbursable Agreement, 2. Map, 3. Riviera Utilities - Reimbursable Agreement (Approved 5-17-2022)

Meeting Type:   BCC Regular Meeting

Meeting Date:  11/7/2023

Item Status:   New

From: Frank Lundy, P.E., County Engineer
           Mark Acreman, P.E., Assistant County Engineer
           Seth Peterson, P.E., Pre-Construction Manager

Submitted by:  John Sedlack, Design Tech III

______________________________________________________________________

 

ITEM TITLE

Title

Rescinding and Approving Supplemental Reimbursable Utility Agreement - County Road 13 at County Road 44 Roundabout

End

STAFF RECOMMENDATION

Recommendation

Take the following actions:

1) Rescind the action taken by the Baldwin County Commission during its regularly scheduled meeting on September 5, 2023, more specifically, the Staff recommendation regarding Agenda item CO5, which approved as follows:

“Approve a Supplemental Utility Agreement between the Baldwin County Commission and Riviera Utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. Total cost of this supplemental relocation work is $94,564.53 with the Alabama Department of Transportation (ALDOT) providing $85,108.08 (90%) and Baldwin County providing $9,456.45 (10%). (This agreement shall be effective upon full execution and will terminate upon completion of the project.)”

2) Approve a Supplemental Utility Agreement between the Baldwin County Commission and Riviera Utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. Total cost of this supplemental relocation work is $95,014.53 with the Alabama Department of Transportation (ALDOT) providing $85,513.07 (90%) and Baldwin County providing $9,501.46 (10%). (This agreement shall be effective upon full execution and will terminate upon completion of the project.)

End

BACKGROUND INFORMATION

 

Background:  This supplemental agreement was approved on September 5, 2023. An error in the agreement amount was found before it was executed by the Alabama Department of Transportation (ALDOT). A corrected agreement will be executed in its place. 

 

Previous Commission action/date: 

September 5, 2023 - Approved a Supplemental Utility Agreement between the Baldwin County Commission and Riviera Utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. Total cost of this supplemental relocation work is $94,564.53 with the Alabama Department of Transportation (ALDOT) providing $85,108.08 (90%) and Baldwin County providing $9,456.45 (10%). (This agreement shall be effective upon full execution and will terminate upon completion of the project.)

 

May 17, 2022 - Approved a Reimbursable Utility Agreement between the Baldwin County Commission and Riviera Utilities for the relocation of utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. Total cost of this relocation is $137,278.26 with the Alabama Department of Transportation (ALDOT) providing a 90% match of $123,550.43 and Baldwin County providing the remaining 10% of $13,727.83 (This agreement shall be effective upon full execution and will terminate upon completion of the project.)

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $95,014.53 - Of this amount, the Alabama Department of Transportation (ALDOT) is providing a 90% match ($85,513.07) and Baldwin County is providing the remaining 10% ($9,501.46.)

 

Budget line item(s) to be used:  HW18069000-3UTILITY-3CONTRSRV-3CONTRACT

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

No

 

Reviewed/approved by:  N/A

 

Additional comments:  Standard ALDOT Supplemental Reimbursable Agreement used.

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up:  Administration Staff prepare correspondence and have the Chairman sign agreement. Return to the Highway Department (John Sedlack) for County Engineer signature and for delivery to the Alabama Department of Transportation for final execution.

 

Action required (list contact persons/addresses if documents are to be mailed or emailed): 

Contact:

 

Mr. Thomas W. Goodman, Jr., P.E.

Local Transportation Engineer - Mobile

Alabama Department of Transportation

1701 I-65 Service Road N

Mobile, Alabama 36618

 

Additional instructions/notes:  Administration -remove rescinded item from tickler and add approve item to tickler