Agenda item title: Competitive Bid #WG22-60A - Provision of Fiber Optic Network-Maintenance and Locates for the Baldwin County Commission
Attachments: 1. 2nd Extension Email Agreement from B&L Cable Construction 20240916, 2. Competitive Bid WG22-60A Award Listing, 3. Contract for Professional and Construction Services 20221101

Meeting Type:   BCC Regular Meeting

Meeting Date:  10/1/2024

Item Status:   New

From: Wanda Gautney, Purchasing Director; Brian Peacock, CIS Director; Adam Scarborough, Assistant CIS Director

Submitted by:  Jeanette Brown, Assistant Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Competitive Bid #WG22-60A - Provision of Fiber Optic Network-Maintenance and Locates for the Baldwin County Commission

End

STAFF RECOMMENDATION

Recommendation

Extend Bid #WG22-60A - Provision of Network-Maintenance and Locates with B & L Cable Construction, LLC, for an additional twelve (12) months at the same prices, terms, and conditions stated in the original bid award on November 1, 2022.

The Contract extension will expire on November 1, 2025.

End

BACKGROUND INFORMATION

 

Background:  The CIS staff requests that the Commission extend the bid for the Provision of Fiber Optic Network-Maintenance and Locates with B & L Cable Construction, LLC, that was awarded on November 1, 2022.  The bid specifications contained a stipulation that the bid could be extended for two (2) additional twelve (12) month periods by the Commission at their option, if acceptable by the vendor, and any additional contract or extensions will be at the same prices, terms and conditions stated in the bid.  The vendor, B & L Cable Construction, LLC, submitted an email agreeing to extend the bid prices for an additional twelve (12) months.  The second Contract extension will expire on November 1, 2025.  Award Listing and Contract attached for review.

 

Previous Commission action/date: 

10/03/2023 meeting: Extended Bid #WG22-60A - Provision of Network-Maintenance and Locates with B & L Cable Construction, LLC, for an additional twelve (12) months at the same prices, terms, and conditions stated in the original bid award on November 1, 2022.  The Contract extension will expire on November 1, 2024.

 

11/01/2022 meeting: Awarded Bid #WG22-60A to the lowest bidder, B & L Cable Construction, LLC, for the Provision of Fiber Optic Network-Maintenance and Locates, per the Award Listing and authorized the Chairman to execute the Contract. (Contract is for twelve (12) months and commences immediately upon the same date as full execution, with an option to issue two (2) twelve (12) month contracts).

09/20/2022 meeting: Authorized the Purchasing Director to re-bid the Provision of Fiber Optic Network-Maintenance and Locates; and further, authorized the Chairman/Purchasing Division Commissioner for the Baldwin County Commission to approve any necessary addendums or clarifications if required after the bid was advertised.

08/02/2022 meeting: Authorized the Purchasing Director to place a competitive bid for the Provision of Fiber Optic Network-Maintenance and Locates for the Baldwin County Commission, further, authorized the Chairman/Purchasing Division Commissioner for the Baldwin County Commission to approve any necessary addendums or clarifications if required after the bid was advertised.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $8,210.00 per month ($98,520.00 Annually)

 

Budget line item(s) to be used:  10051101.52290

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  10/01/2024

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Vendor

 

Additional instructions/notes:  Admin - update expiration date in Contracts.