ITEM TITLE
Title
Competitive Bid #WG18-25 - Construction of Magnolia Landfill Gas Collection System - Phase 3 Expansion for the Baldwin County Commission
Body
STAFF RECOMMENDATION
Recommendation
Take the following actions:
1) Award the bid to the lowest responsible bidder, who met all the specifications, Stearns, Conrad & Schmidt, Consulting Engineers, Inc., d/b/a SCS Field Services
in the amount of $497,540.00; Completion Time: 90 days after Notice to Proceed for the Construction of Magnolia Landfill Gas Collection System - Phase 3 Expansion and authorize the Chairman to execute Contract; and
2) Authorize the Chairman to execute any project related documents.
End
BACKGROUND INFORMATION
Previous Commission action/date:
3/06/18 meeting: Authorized the Purchasing Director and CDG Engineers to advertise for the Pre-Qualification of Contractors for the construction of Magnolia Landfill Gas Collection System - Phase 3 Expansion.
5/01/18 meeting: 1) Rejected the application receive from H & M Construction Co., LLC, as non-qualified; and 2) Approve the following two (2) applications:
Advance One Development, LLC; and Stearns, Conrad & Schmidt, Consulting Engineers, Inc., d/b/a SCS Field Services; and 3) Authorized the Purchasing Director and Engineer, CDG Engineers to bid the project.
Background: Bids were opened in the Purchasing Conference Room on May 22, 2018, at 2:00 P.M. Two (2) bids were received. Advanced One Development, LLC,
submitted the lowest bid price but cannot be awarded the bid because there Alabama General Contractors License only possess a (BC): Building Construction classification.
This project is installing a Landfill Gas Collection System involving a large amount of piping and no building. Per the Alabama General Contractor Board Chief Investigator,
Advance One Development, LLC, bid outside their classification, putting them in violation of Alabama Code Sections 34-8-1 through 34-8-10, A Contractor Bidding Outside Classification. The lowest responsible bid was received from Stearns, Conrad & Schmidt, Consulting Engineers, Inc., d/b/a SCS Field Services in the amount of
$497,540.00 with a completion time of 90 days after Notice to Proceed. The Engineer with CDG Engineers & Associates, Inc., Daniel Wells, has reviewed the bid responses and has submitted the certified Bid Tabulation and a letter recommending that the bid be awarded to the lowest responsible bidder, Stearns, Conrad & Schmidt, Consulting Engineers, Inc., d/b/a SCS Field Services. Bid Tabulation attached.
FINANCIAL IMPACT
Total cost of recommendation: $497,540.00
Budget line item(s) to be used: 54300.5500
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
N/A
Reviewed/approved by: N/A
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: 6/19/2018
Individual(s) responsible for follow up: Wanda Gautney/Purchasing Director
Action required (list contact persons/addresses if documents are to be mailed or emailed): Letter to Bidders