Baldwin County Regional Juvenile Detention Center - Ditch Grading and Placement of Sod
Body
STAFF RECOMMENDATION
Recommendation
Approve the Highway Department to do ditch grading and place sod at the Baldwin County Regional Juvenile Detention Center for an estimated cost of $2,886.75 for labor and materials.
The Baldwin County Juvenile Detention Center will be invoiced the actual cost for labor and materials upon completion of the project.
End
BACKGROUND INFORMATION
Previous Commission action/date: N/A
Background: The Baldwin County Regional Juvenile Detention Center is requesting assistance from the Commission to reshape the ditch for positive flow in front of the building and add sod.
FINANCIAL IMPACT
Total cost of recommendation: N/A
Budget line item(s) to be used: N/A
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
N/A
Reviewed/approved by: N/A
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: N/A
Individual(s) responsible for follow up: Area 100 schedule project. Highway Accounting send invoice to Juvenile Detention Center upon completion of project.
Contact:
Ron Ballard
43405 Nicholsville Road
Bay Minette, Alabama 36507
Action required (list contact persons/addresses if documents are to be mailed or emailed): N/A
Additional instructions/notes: N/A