Baldwin County, Alabama
File #: 19-0129    Version: 1
Agenda section: Consent Status: Passed
File created: 10/23/2018 Meeting type: Baldwin County Commission Regular
On agenda: 11/6/2018 Final action: 11/6/2018
Agenda item title: Competitive Bid #WG18-35 - Renovations of the Restrooms in the Baldwin County Satellite Courthouse Located in Foley, Alabama for the Baldwin County Commission
Attachments: 1. BCSCH. CO#1. Restroom Renovation, 2. *BE3 - Highland Wake Construction, LLC - Change Order No. 1

Meeting Type:   BCC Regular Meeting

Meeting Date:  11/6/2018

Item Status:   New

From: Wanda Gautney, Purchasing Director; Junius Long, Building Facilities Coordinator

Submitted by:  Wanda Gautney, Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Competitive Bid #WG18-35 - Renovations of the Restrooms in the Baldwin County Satellite Courthouse Located in Foley, Alabama for the Baldwin County Commission

Body

 

STAFF RECOMMENDATION

Recommendation

Approve the attached Change Order #1 in the amount of $5,544.00 with Highland Wake Construction, LLC, for the Renovations of the Restrooms in the Baldwin County Satellite Courthouse located in Foley, Alabama, and authorize the Chairman to execute the Change Order.

End

 

BACKGROUND INFORMATION

 

Previous Commission action/date: 

08/21/2018 meeting:  Awarded Bid #WG18-35 - Renovations of the Restrooms in the Baldwin County Satellite Courthouse located in Foley, Alabama to the lowest bidder, Highland Wake Construction, LLC, in the bid amount of $110,697.23; Completion Time: 105 Calendar Days; and authorize the Chairman to execute the Contract.

 

07/03/2018 meeting: 1) Approved the specifications and authorized the Purchasing Director to place a competitive bid for the renovations of the restrooms located in the Foley Satellite Courthouse; and 2) Further, authorized the Chairman/Purchasing Division Commissioner for the Baldwin County Commission to approve any necessary addendums or clarifications if required after the bid is advertised.

 

Background:  The Building Facilities Coordinator, Junius Long is submitting for Commission approval, Change Order #1 in the amount of $5,544.00, to replace all eleven (11) floor drains in the restrooms that have rusted out and were found during the demolition. The original construction cost is $110,697.23 including Change Order #1 the new cost will be $116,241.23.

 

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $5,544.00

 

Budget line item(s) to be used:  51995.5231

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  11/06/2018

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Vendor

 

Additional instructions/notes:  N/A