Baldwin County, Alabama
File #: 19-0137    Version: 1
Agenda section: Consent Status: Passed
File created: 10/23/2018 Meeting type: Baldwin County Commission Regular
On agenda: 11/6/2018 Final action: 11/6/2018
Agenda item title: Case No. S-16053a - The Verandas, Phase 2
Attachments: 1. Subdivision Roadway and Drainage Improvement Acceptance Agreement, 2. Exhibit A - Cost Estimate, 3. Exhibit B - Maintenance Bond (REDACTED), 4. Exhibit C - Recorded Plat, 5. Exhibit D - Certification of Improvements, 6. Plat Review Letter, 7. Permission to Date Bond (REDACTED), 8. Vicinity Map, 9. Site Map

Meeting Type:   BCC Regular Meeting

Meeting Date:  11/6/2018

Item Status:   New

From: Joey Nunnally, P.E., County Engineer
Seth Peterson, P.E. Permit/Subdivision Manager

Submitted by:  Laurie Rumbaugh, Office Administrator

______________________________________________________________________

 

ITEM TITLE

Title

Case No. S-16053a - The Verandas, Phase 2

 

Body

 

STAFF RECOMMENDATION

Recommendation

Take the following actions:

 

1) Approve the following subdivision roads for maintenance and authorize said roads to be added to the County Maintenance Road List:

 

Street Name                                                    Length   Maint. Area    Asphalt Width    Curbing

 

Veranda Boulevard                             2,477                                          200               18                                Yes

Catana Avenue                                     48                                 200               18                                       Yes

Turin Avenue                                      165                                  200               18                                       Yes

Naples Avenue                                   634                                  200               18                                       Yes

Pillars Street                                       698                                  200               18                                       Yes

 

2) Approve the Subdivision Roadway and Drainage Improvement Acceptance Agreement and accept the Surety Document from Fidelity and Deposit Company of Maryland on behalf of Ammons and Blackmon Construction, LLC in the amount of $251,532.40 to guarantee the workmanship and materials as shown on the approved Final and “As-built” Construction Plans.

 

End

 

BACKGROUND INFORMATION

 

Previous Commission action/date:  N/A

 

Background:  On May 31, 2018, the Baldwin County Highway Department, Permit Section approved the Final and “As-built” Construction Drawings for The Veranda, Ph 2 (County Case No. S-16053a) located on State Highway 104 in the Fairhope area.

 

The Baldwin County Subdivision Regulations, Article §7.4.2 - Maintenance Surety, requires the following:

(a)                     Acceptance of Maintenance Surety Document.  The surety document must first be reviewed by the County Engineer and Chief Legal Counsel, and then accepted and approved by the County Commission;

 

(b)                     Value of Maintenance Surety Document.  The maintenance surety document shall be of an amount equal to or greater than 40 percent of the cost (Itemized Engineer’s Cost Estimate) of the full construction of the required roadway and drainage improvements within the public rights-of-way, including but not limited to, grading, paving of the streets, and installation of stormwater structures. When the County Engineer identifies potential problems, conditions or reasons for further protection of the County and public funds a greater amount may be required by the County Engineer;

 

(c)                     Term pf Maintenance Surety Document. A maintenance surety document must state that it is “valid for a period of time” as prescribed in the Subdivision Roadway and Drainage Improvement Acceptance Agreement. A twenty-four (24) month warranty period will begin to run upon the occurrence of both of the following (a) the County Commission votes in the affirmative to accept for maintenance the roadway and drainage improvements, within the public rights-of-way; and (b) the maintenance surety document in acceptable form is delivered to the Baldwin County Commission.

 

Notwithstanding the above requirements, this warranty period shall be automatically extended in the event that an invoice has been sent to the Owner and the time of the subject invoice conflicts with, or the necessary repairs extend beyond, the final date of the twenty-four (24) month warranty period. In such event, said maintenance surety document shall remain in full effect until the Baldwin County Commission releases said surety document following the fulfillment of all obligations to the Baldwin County Commission as required by the Subdivision Roadway and Drainage Improvement Acceptance Agreement.

The value and terms of the surety have been reviewed by Highway Department Staff and are consistent with the requirements of the Baldwin County Subdivision Regulations (see attached cost estimate).

 

FINANCIAL IMPACT

 

Total cost of recommendation:  N/A

 

Budget line item(s) to be used:  N/A

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  Standard form used as previously approved by the County Attorney.

 

Additional comments:  N/A

 

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up:  Administration Staff; Permit Division

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Administration Staff to have Commission Chairman and County Administrator execute Subdivision Roadway Acceptance Agreement and return the signed document to the Permit Division.  Permit Division will notify all appropriate County Highway personnel to begin maintenance.

 

Additional instructions/notes:  N/A