Highway Safety Improvement Program (HSIP) - Project Funding Application for Intersection Improvements at US Highway 31 and Old Highway 31 in Spanish Fort
Body
STAFF RECOMMENDATION
Recommendation
Take the following actions:
1. Authorize the Highway Department to submit a project funding application to the Alabama Department of Transportation (ALDOT) for a Highway Safety Improvement Program (HSIP) Intersection Improvements Project at US Highway 31 and Old Highway 31 in Spanish Fort; and
2. Authorize the Chairman to execute a letter of intent and any other application related documents as required.
End
BACKGROUND INFORMATION
Previous Commission action/date: N/A
Background: The Highway Department is requesting permission to submit an application under the HSIP for an Intersection Improvements Project at US Highway 31 and Old Highway 31 in Spanish Fort. Under the HSIP program, the Federal contribution would be 90%, and the County, as Sponsor, would provide a 10% contribution. The estimated project cost is $363,500.00. The County’s estimated portion would be $36,350.00. If grant is approved, construction match will be budgeted in Fiscal Year 2020. Funding for Design would come from Highway Fiscal Year 2019 annual budgeted Engineering Services.
FINANCIAL IMPACT
Total cost of recommendation: $36,350.00 estimated
Budget line item(s) to be used: Design - 53600.5165 - $10,000.00
Construction - Fiscal Year 2020 Budget - $26,350.00
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
N/A
Reviewed/approved by: N/A
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: N/A
Individual(s) responsible for follow up:
Commission Staff have Chairman sign letter of intent and project application forms and return to Highway Department - John Sedlack
Highway Department submit application to the Alabama Department of Transportation for consideration of approval.
Action required (list contact persons/addresses if documents are to be mailed or emailed):
Mail Correspondence:
John-Michael Walker, P.E.
State Traffic and Safety Operations Engineer
Traffic Safety Operations Section
Design Bureau
Alabama Department of Transportation
1409 Coliseum Boulevard
Montgomery, Alabama 36110
Additional instructions/notes: N/A