Agenda item title: Resolution No. 2020-027 and Construction Funding Agreement for Intersection Improvements at County Road 71 at State Route 59 and Signal Installation at County Road 28 and State Route 59
Attachments: 1. Agreement, 2. CR 28 at SR 59 Signal Map, 3. CR 28 at SR 59 with Annexations Map, 4. CR 71 at SR 59 Intersection Improvements, 5. *GN2 - Resolution 2020-027 SIGNED

Meeting Type:   BCC Regular Meeting

Meeting Date:  11/19/2019

Item Status:   New

From: Joey Nunnally, P.E., County Engineer

Submitted by:  John Sedlack, Design Tech III

______________________________________________________________________

 

ITEM TITLE

Title

Resolution No. 2020-027 and Construction Funding Agreement for Intersection Improvements at County Road 71 at State Route 59 and Signal Installation at County Road 28 and State Route 59

 

Body

STAFF RECOMMENDATION

Recommendation

Approve Resolution No. 2020-027 and authorize the Chairman to execute a construction funding agreement with the Alabama Department of Transportation (ALDOT) for the following:

 

1) Intersection improvements at County Road 71 at State Route 59 for an estimated cost of $105,058.83 with ALDOT funding the project; and

 

2) Signal installation at County Road 28 and State Route 59 for an estimated cost of $209,402.64 with ALDOT and Baldwin County each providing 50% ($104,701.32).

 

(Agreement shall be effective on the date of the approval of the Governor of Alabama and shall terminate on January 1, 2022, unless terminated by either party upon the delivery of a thirty (30) day notice of termination.)

End

 

BACKGROUND INFORMATION

 

Previous Commission action/date:  N/A

 

Background: 

The Alabama Department of Transportation and Baldwin County Highway Department have determined the need for intersection improvements at County Road 71 and State Route 59 and the installation of a traffic signal at County Road 28 and State Route 59. The intersection improvements at County Road 71 and State Route 59 will be funded 100% by ALDOT at an estimated cost of $105,058.83 and the installation of a traffic signal at County Road 28 and State Route 59 will be split 50/50 with ALDOT at an estimated cost of $209,402.64 with each providing $104,701.32.

 

The Town of Summerdale has agreed to assist the County with the funding of the traffic signal at County Road 28 and State Route 59 in the amount of $75,000.00.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $104,701.32

 

Budget line item(s) to be used:  0213819.5150

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

No - Standard ALDOT Funding Agreement

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up:  Commission Staff have Resolution and Funding Agreement executed and return to Highway Department (John Sedlack) to submit to ALDOT.

 

Action required (list contact persons/addresses if documents are to be mailed or emailed): 

Mail to address:

 

Matthew J. Ericksen, P.E.

Southwest Region Engineer

1701 I-65 West Service Road N

Mobile, Alabama 36618

 