Agenda item title: S-18037 - Turnberry Crossing, Phase Three - Road Acceptance
Attachments: 1. Vicinity Map, 2. Site Map, 3. Subdivision Roadway and Drainage Improvement Acceptance Agreement, 4. Exhibit A - Engineer's Itemized Cost Estimate of Construction, 5. Exhibit B - Maintenance Bond (REDACTED), 6. Exhibit C - Recorded Plat, 7. Exhibit D - Certificate of Improvements for Subdivisions, 8. Plat Review Letter, 9. Common Area Maintenance Letter
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

Meeting Type:   BCC Work Session

Meeting Date:  1/14/2020

Item Status:   New

From: Joey Nunnally, P.E., County Engineer
           Tyler Mitchell, P.E., Construction Manager

Submitted by:  Kristen Rawson, Office Manager

______________________________________________________________________

 

ITEM TITLE

Title

S-18037 - Turnberry Crossing, Phase Three - Road Acceptance

 

Body

STAFF RECOMMENDATION

Recommendation

Take the following actions regarding Subdivision Case No. S-18037 - Turnberry Crossing, Phase Three in Maintenance Area 300:

 

1) Accept the following subdivision roads for maintenance and authorize said roads to be added to the County Maintenance Road List:

 

Road Name                                                                Length                               Asphalt Width

Kudu Avenue                                           438 ft                                                                                    20

Sitka Drive                                                                924 ft                                                                                    20

Impala Drive                                                                335 ft                                                                                    20

 

2) Approve and authorize the Chairman to execute the Subdivision Roadway and Drainage Improvement Acceptance Agreement and accept the Surety Document from Fidelity and Deposit Company on behalf of Ammons & Blackmon Construction, LLC in the amount of $139,535.64 to guarantee the workmanship and materials of the roadways and drainage improvements within the public rights-of-way as shown on the approved Final and “As-Built” construction plans.

 

End

BACKGROUND INFORMATION

 

Previous Commission action/date:  N/A

 

Background:  On November 8, 2019, the Baldwin County Highway Department approved the Final and “As-Built” Construction Plans for Turnberry Crossing, Phase Three (County Case S-18037) located in Foley. The required improvements have been inspected and are in accordance with the Subdivision Regulations.

 

The Baldwin County Subdivision Regulations, Article §7.4.2 - Maintenance Surety Document, requires the following:

 

a) Acceptance of Maintenance Surety Document. The surety document must first be reviewed by the County Engineer and Chief Legal Counsel, and then accepted and approved by the County Commission;

 

b) Value of Maintenance Surety Document. The maintenance surety shall be of an amount equal to or greater than 40 percent of the cost (Itemized Engineer’s Cost Estimate) of the full construction of the required roadway and drainage improvements within the public rights-of-way, including but not limited to, grading, paving of the streets, and installation of stormwater structures. When the County Engineer identifies potential problems, conditions or reasons for further protection of the County and public funds a greater amount may be required by the County Engineer;

 

c) Term of Maintenance Surety Document. A maintenance surety document must state that it is “valid for a period of time” as prescribed in the Subdivision Roadway and Drainage Improvement Acceptance Agreement. A twenty-four (24) month warranty period will begin to run upon the occurrence of both of the following (a) the County Commission votes in the affirmative to accept for maintenance the roadway and drainage improvements, within the public rights-of-way; and (b) the maintenance surety document in acceptable form is delivered to the Baldwin County Commission.

 

Notwithstanding the above requirements, this warranty period shall be automatically extended in the event that an invoice has been sent to the Owner and the time of the subject invoice conflicts with, of the necessary repairs extend beyond, the final date of the twenty-four (24) month warranty period. In such event, said maintenance surety document shall remain in full effect until the Baldwin County Commission releases said surety document following the fulfillment of all obligations to the Baldwin County Commission as required by the Subdivision Roadway and Drainage Improvement Acceptance Agreement.

 

The value and terms of the surety have been reviewed by Highway Department Staff and are consistent with the requirements of the Baldwin County Subdivision Regulations (see attached Cost Estimate).

 

FINANCIAL IMPACT

 

Total cost of recommendation:  N/A

 

Budget line item(s) to be used:  N/A

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

Yes

 

Reviewed/approved by:  County Attorney is currently reviewing.

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up:  Administration Staff to have Commission Chairman and County Administrator execute Subdivision Roadway Acceptance Agreement and return signed document to Kristen Rawson (Highway Department). Appropriate Highway Department Personnel will be notified to begin maintenance.

 

Action required (list contact persons/addresses if documents are to be mailed or emailed): 

 

Please send correspondence to:

 

Contact:

Rance Reehl

Turnberry Crossing 2016, LLC

24190 U.S. Highway 98, Suite B

Fairhope, Alabama  36532

 