Meeting Type: BCC Regular Meeting
Meeting Date: 10/6/2020
Item Status: Addendum
From: Joey Nunnally, P.E., County Engineer
Tyler Mitchell, P.E., Construction Manager
Mike Campbell, Engineering Technician I
Submitted by: Lisa Sangster, Administrative Support Specialist IV
______________________________________________________________________
ITEM TITLE
Title
License Agreement No. 20031 - Right of Way off State Highway 180
Body
STAFF RECOMMENDATION
Recommendation
Approve License Agreement No. 20031 permitting J.C. House, III, to access right-of-way off State Highway 180 for hauling in sand and gravel to rebuild his existing driveway. (The term of this agreement shall commence on the date of full execution. License for Installation shall terminate at 11:59 on October 6, 2021. License for Maintenance shall be indefinite according to the terms of the agreement.)
End
BACKGROUND INFORMATION
Previous Commission action/date: N/A
Background: J.C. House, III, is requesting access to right-of-way off State Highway 180 for the purpose of hauling in sand and gravel to rebuild his existing driveway, approximately 597 feet long, that was damaged due to Hurricane Sally.
FINANCIAL IMPACT
Total cost of recommendation: N/A
Budget line item(s) to be used: N/A
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
N/A
Reviewed/approved by: N/A
Additional comments: Standard agreement used as previously approved by Laura Coker (02/11/2020) los
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: N/A
Individual(s) responsible for follow up: Administration Staff have license agreement executed by the Chairman and the original forwarded to the County Engineer. Mike Campbell will issue the license agreement and conduct all necessary follow-up inspections on work performed.
Action required (list contact persons/addresses if documents are to be mailed or emailed): N/A
Additional instructions/notes: N/A