Agenda item title: Pre-qualification of Contractors for the Construction of Two (2) New Baldwin County Highway Maintenance Buildings Located in Bay Minette, and Silverhill, Alabama
Attachments: 1. Proof of Advertisements Hwy Bldgs.

Meeting Type:   BCC Regular Meeting

Meeting Date:  11/3/2020

Item Status:   New

From: Wanda Gautney, Purchasing Director/Joey Nunnally, County Engineer/Nic Gray, Watermark Design Group, LLC

Submitted by:  Loren Lucas, Assistant Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Pre-qualification of Contractors for the Construction of Two (2) New Baldwin County Highway Maintenance Buildings Located in Bay Minette, and Silverhill, Alabama

Body

 

STAFF RECOMMENDATION

Recommendation

Take the following actions:

 

1)  Approve the following ten (10) pre-qualification applications on the Construction of Two (2) Highway Maintenance Buildings: Witherington Construction Corporation, FITZgerald Construction, LLC, Thomas Industries, Inc. d/b/a Thomas Construction, White-Spunner Construction, Inc., Sycamore Construction, Inc., J T Harrison Construction Co., Inc., Parsco, LLC d/b/a Parsco Construction, LLC, Lord & Son Construction, Inc., Ben M Radcliff Contractor, Inc., and Eric Lazzari Construction, LLC; and

 

2)  Reject the applications of the following ten (10) applicants as non-qualified: The Highland Group, Bayshore Construction Co., Inc., D & B Builders, Inc., Stephens Construction and Concrete, Inc., PCI Support Services, LLC, Abuck Incorporated, G A West & Company, Inc., Gordon & Zakary, Inc., M W Rogers Construction Co., LLC, and Triptek Construction, LLC; and

 

3)  Authorize the Purchasing Director and the Architect to bid the project.

End

 

BACKGROUND INFORMATION

 

Previous Commission action/date: 

03/17/2020 meeting:  Approved the attached AIA Contract for the architectural services with Watermark Design Group, LLC, for the design of a two (2) new Baldwin County Area 100 and Area 200 Highway Maintenance Facilities located in Bay Minette, and Silverhill,  Alabama in the amount of 6% of the construction cost for the new plus normal reimbursable expenses and authorize the Chairman to execute the Contracts.

 

07/07/2020 meeting: Authorized the Purchasing Director to advertise for the Pre-qualification of Contractors for the construction of two (2) new Baldwin County Highway Maintenance Buildings Located in Bay Minette, and Silverhill, Alabama.

 

08/18/2020 meeting: Rejected all fourteen (14) applications received due to incomplete proposals on the construction of two (2) new Baldwin County Highway Maintenance Buildings located in Bay Minette, and Silverhill, Alabama projects; and 2) Authorized the Purchasing Director to re-advertise for the Pre-qualification of Contractors for the construction of two (2) new Baldwin County Highway Maintenance Buildings Located in Bay Minette, and Silverhill, Alabama.

 

Background:  The Pre-Qualification applications of the Contractors were received in the Purchasing Office on September 10, 2020, at 2:30 p.m.  Twenty (20) applications were received.  Staff members Wanda Gautney, Ron Cink, Cian Harrison, Joey Nunnally, Seth Peterson, Beth Burnett, Loren Lucas and Dana Austin, met on October 8, 2020 at 9:00 a.m. to review the applications.  The staff’s recommendation is to approve the following ten (10) pre-qualification applications: Witherington Construction Corporation, FITZgerald Construction, LLC, Thomas Industries, Inc. d/b/a Thomas Construction, White-Spunner Construction, Inc., Sycamore Construction, Inc., J T Harrison Construction Co., Inc., Parsco, LLC d/b/a Parsco Construction, LLC, Lord & Son Construction, Inc., Ben M Radcliff Contractor, Inc., and Eric Lazzari Construction, LLC; reject the following ten (10) applicants as non-qualified due to incomplete applications: The Highland Group, Bayshore Construction Co., Inc., D & B Builders, Inc., Stephens Construction and Concrete, Inc., PCI Support Services, LLC, Abuck Incorporated, G A West & Company, Inc., Gordon & Zakary, Inc., M W Rogers Construction Co., LLC, and Triptek Construction, LLC, and authorize the Purchasing Director and the Architect to bid the project.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  N/A

 

Budget line item(s) to be used:  N/A

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  Yes

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  11/04/2020

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Applicants

 

Additional instructions/notes:  N/A