Agenda item title: Project No. BCP 0203120 (HW20031000) - Construction of the Baldwin County Intracoastal Waterway (ICW) Boat Launch
Attachments: 1. ICW Engineer Award Recommendation Letter, 2. ICW Certified Bid Tabulation, 3. IX Contract ICW Project, 4. Proof of Advertisements for ICW Project

Meeting Type:   BCC Regular Meeting

Meeting Date:  5/18/2021

Item Status:   New

From: Wanda Gautney, Purchasing Director/Joey Nunnally, County Engineer/Seth Peterson, Pre-Construction Manager

Submitted by:  Wanda Gautney, Purchasing Director

______________________________________________________________________

 

ITEM TITLE

Title

Project No. BCP 0203120 (HW20031000) - Construction of the Baldwin County Intracoastal Waterway (ICW) Boat Launch

Body

 

STAFF RECOMMENDATION

Recommendation

Take the following actions:

1)  Award the bid for Project No. BCP 0203120 (HW20031000) Construction of the Baldwin County Intracoastal Waterway (ICW) Boat Launch to the lowest bidder, McElhenney Construction Co., LLC, as follows and authorize the Chairman to execute the Contract.

Base Bid Amount:  $9,124,235.15
Additive #3:             $   104,418.32 (Covered Breezeway)
Decking Alternate: 
$   163,334.53 (Decking)
TOTAL AMOUNT:    $9,391,988.00
Construction Time: 100 Working Days

2)  Not awarding Additive #1 (Fishing Pier) $597,241.62 and Additive #2 (Walking Trail) $209,628.45.

 

3)  Approve and confirm funding for this project from various sources:

                     a. 2.6M State GOMESA Grant

                     b. 3.1M Baldwin County 2021 GOMESA allocation

                     c. 2.0M 2020 Baldwin County GOMESA allocation reassigned from County Road 6 project

                     d. 3.0M 2018-2019 Baldwin County GOMESA allocation approved at the 01/19/2021 regular

                     meeting.

 

Total $10.7M which comprehends an additional $1.3M needed for associated projects at the launch.

 

 

BACKGROUND INFORMATION

 

Previous Commission action/date: 

12/03/2019 meeting:  Adopted Resolution #2020-038 amending the Fiscal Year 2020 Budget (Resolution #2019-144 adopted September 20, 2019) to authorize the movement of $400,000.00 from General Fund (Fund 001) to Parks (Fund 144) for the design of the Intracoastal Waterway Boat Launch.

 

02/04/2020 meeting:  Waived Baldwin County Policy #9.10-Engineering and Surveying Services, and approved on-call consultant, Volkert, Inc., to perform design services for the Intracoastal Waterway Boat Launch Design with design fees not to exceed $399,931.00.

 

01/05/2021 meeting:  Authorized the Chairman to execute the Gulf of Mexico Energy Security Act (GOMESA) Grant Agreement with the Alabama Department of Conservation and Natural Resources (ADCNR) for public access improvements at the Baldwin County Intracoastal Waterway (ICW) boat ramp; and authorized the Chairman to execute any other project related documents.

 

01/19/2021 meeting:  Approved funding for the Intracoastal Waterway (ICW) Boat Launch construction using $3,000,000.00 of Gulf of Mexico Energy Security Act (GOMESA) funds.

 

02/17/2021 meeting: 1) Approved the Purchasing Director to place a competitive bid for the Baldwin County Intracoastal Waterway (ICW) Boat Launch Construction Project; and 2) Approved the Chairman to execute any project related documents.

 

Background:  Bids were opened in the Purchasing Conference Room on May 4, 2021, at 2:00 p.m.  Two (2) bids were received.  The lowest was received from McElhenney Construction Co., LLC, in the base bid amount of $9,124,235.15.  The bid included three (3) Additives and one (1) Alternate.  The Highway Department is recommending the Commission award Additive #3 (Covered Breezeway) in the amount of $104,418.32 and the Alternate for Decking in the amount of $163,334.53 and not award Additive #1 (Fishing Pier) $597,241.62 and Additive #2 ((Walking Trail) $209,628.45. The Baldwin County Engineer, Joey Nunnally, has reviewed the bid responses and has submitted the certified Bid Tabulation and a letter recommending that the bid be awarded to the lowest, McElhenney Construction Co., LLC., in the base bid amount of $9,124,235.15; Additive #3 $104,418.32 (Covered Breezeway) and Decking Alternate $163,334.53; with Construction Time: 100 Working Days.  Bid Tabulation is attached.

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $9,391,988.00

 

Budget line item(s) to be used:  HW20031000

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A.

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

Standard County Construction Contract

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  Yes

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  5/18/2021

 

Individual(s) responsible for follow up:  Wanda Gautney, Purchasing Director

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Letter to Bidders

 