Meeting Type: BCC Regular Meeting
Meeting Date: 10/19/2021
Item Status: New
From: Joey Nunnally, P.E., County Engineer
Submitted by: John Sedlack, Design Tech III
______________________________________________________________________
ITEM TITLE
Title
County Road 20 Extension from South Hickory Street to County Road 65 - Engineering and Survey Services Fee Increase
Body
STAFF RECOMMENDATION
Recommendation
Approve a fee increase of $137,500.00 for additional design services performed by TTL, Inc. for the County Road 20 Extension from South Hickory Street to County Road 65.
End
BACKGROUND INFORMATION
Previous Commission action/date:
March 2, 2021: The Commission waived Baldwin County Commission Policy #9.10 - Engineering, Environmental Monitoring and Surveying Services and approved on-call consultant TTL, Inc., to perform design services for the County Road 20 Extension Project with design fees not to exceed $250,000.00.
September 22, 2020: The Commission adopted Resolution #2020-127 and approved the FY 2021 Budget allocating $535,000.00 for Design and Right-of-Way for the County Road 20 Extension Project.
Background:
Traffic studies performed on S. Hickory Street and County Road 65 recommend that a traffic signal be installed at the intersection of County Road 20 and S. Hickory Street and a roundabout be installed at the intersection of County Road 20 and County Road 65. The design for these intersection improvements will be added to the in-progress County Road 20 extension design.
FINANCIAL IMPACT
Total cost of recommendation: $137,500.00
Budget line item(s) to be used: HW21101000.1PRECN.1CONTR SRV.1CONTRACT
If this is not a budgeted expenditure, does the recommendation create a need for funding? N/A
LEGAL IMPACT
Is legal review necessary for this staff recommendation and related documents?
N/A
Reviewed/approved by: N/A
Additional comments: N/A
ADVERTISING REQUIREMENTS
Is advertising required for this recommendation? N/A
If the proof of publication affidavit is not attached, list the reason: N/A
FOLLOW UP IMPLEMENTATION
For time-sensitive follow up, select deadline date for follow up: N/A
Individual(s) responsible for follow up:
Highway Department staff will issue a “Notice to Proceed” to TTL. Inc.
Action required (list contact persons/addresses if documents are to be mailed or emailed): N/A