Baldwin County, Alabama
File #: 22-1352    Version: 1
Agenda section: Consent Status: Agenda Ready
File created: 8/4/2022 Meeting type: Baldwin County Commission Regular
On agenda: 8/16/2022 Final action:
Agenda item title: County Road 13 at County Road 44 Roundabout - Reimbursable Utility Agreement
Attachments: 1. Utility Relocate Engineering Agreements Roundabout CR13&CR44, 2. Map

Meeting Type:   BCC Regular Meeting

Meeting Date:  8/16/2022

Item Status:   New

From: Joey Nunnally, P.E., County Engineer
           Seth Peterson, P.E., Pre-Construction Manager

Submitted by:  John Sedlack, Design Tech III

______________________________________________________________________

 

ITEM TITLE

Title

County Road 13 at County Road 44 Roundabout - Reimbursable Utility Agreement

 

End

STAFF RECOMMENDATION

Recommendation

Approve a Reimbursable Utility Agreement between the Baldwin County Commission and Fairhope Utilities for the relocation of utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. Total cost of this relocation is $428,889.29 with the Alabama Department of Transportation (ALDOT) providing a 90% match of $386,000.36 and Baldwin County providing the remaining 10% at $42,888.93.

This agreement shall be effective upon full execution and will terminate upon completion of the project.

End

BACKGROUND INFORMATION

 

Background:  The Highway Department has been awarded a grant under the HSIP for a proposed roundabout on County Road 13 and County Road 44. Under the HSIP program, utility relocation is a reimbursable phase of the project.

 

Previous Commission action/date: 

May 17, 2022: 1) Approved a Reimbursable Utility Agreement between the Baldwin County Commission and Riviera Utilities for the relocation of utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. Total cost of this relocation is $137,278.26 with the Alabama Department of Transportation (ALDOT) providing a 90% match of $123,550.43 and Baldwin County providing the remaining 10% at $13,727.83 (This agreement shall be effective upon full execution and will terminate upon completion of the project.); and 2) Approved a Reimbursable Utility Agreement between the Baldwin County Commission and Baldwin EMC for the relocation of utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. Total cost of this relocation is $26,064.08 with the Alabama Department of Transportation (ALDOT) providing a 90% match of $23,457.67 and Baldwin County providing the remaining 10% at $ 2,606.41(This agreement shall be effective upon full execution and will terminate upon completion of the project.)

May 17, 2022:1) Approved a Non-Reimbursable Utility Agreement between the Baldwin County Commission and Alabama Power Company for the relocation of utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. (This agreement shall be effective upon full execution and will terminate upon completion of the project.); and 2) Approved a Non-Reimbursable Utility Agreement between the Baldwin County Commission and AT&T Communications for the relocation of utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. (This agreement shall be effective upon full execution and will terminate upon completion of the project.); and 3) Approved a Non-Reimbursable Utility Agreement between the Baldwin County Commission and Mediacom for the relocation of utilities to complete the Highway Safety Improvement Project (HSIP) Roundabout Project at County Road 13 and County Road 44. (This agreement shall be effective upon full execution and will terminate upon completion of the project.)

April 5, 2022: Approved an extension to the Intergovernmental Service Agreement with the City of Fairhope for the construction of a roundabout at Twin Beach Road and County Road 13 extending the term of the agreement by thirty-six (36) months.

August 3, 2021: Approved Resolution # 2021-106 and authorized the Chairman to execute Supplemental Agreement No. 1 between the Baldwin County Commission and the Alabama Department of Transportation for the funding of preliminary engineering, right-of-way, utility relocation, construction, and construction engineering inspection for a roundabout at County Road 13 and County Road 44 (Twin Beech Road). (This agreement shall be effective upon full execution and shall be in effect until the project has been completed and reimbursements are complete. This agreement may be terminated by either party upon delivery of a thirty (30) day notice of termination.)

March 19, 2019: Approved Resolution # 2019-058 and authorized the Chairman to execute an agreement between the Baldwin County Commission and the Alabama Department of Transportation for the funding of Preliminary Engineering, Right-of-Way, Utility Relocation, Construction and Construction Engineering Inspection for a Roundabout at County Road 13 and County Road 44 (Twin Beech Road). (This agreement shall be effective upon full execution and shall be in effect until the project has been completed and reimbursements are complete. This agreement may be terminated by either party upon delivery of a thirty (30) day notice of termination.)

February 5, 2019: Approved an Intergovernmental Service Agreement with the City of Fairhope for the construction of a roundabout at Twin Beech Road and County Road 13.

August 21, 2018: Authorized the Highway Department to submit documentation and application for a grant under the Federal Highway Administration -Highway Safety Improvement Program (HSIP) for a proposed roundabout on County Road 13 at County Road 44; and authorize the Chairman to execute a letter of intent and ant other grant related documents as required.

FINANCIAL IMPACT

 

Total cost of recommendation:  $428,889.29 - Of this amount ALDOT is providing a 90% match of $386,000.36 and Baldwin County providing the remaining 10% at $42,888.93.

 

Budget line item(s) to be used:  HW18069000-4CONTRCN-4CONTR SRV-4CONTRACT

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

No

 

Reviewed/approved by:  N/A

 

Additional comments:  Standard ALDOT Reimbursable Agreement used

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up:  Administration Staff prepare correspondence and have the Chairman sign agreement. Return correspondence and signed agreement to Highway Department (John Sedlack) for delivery to ALDOT for final execution.

 

Contact:

Mr. Thomas W. Goodman, Jr. P.E.

Local Transportation Engineer - Mobile

Alabama Department of Transportation

1701 I-65 Service Road North

Mobile, Alabama 36618

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  Administration - upload to BCAP with John Sedlack as originator.

Additional instructions/notes:  N/A