Baldwin County, Alabama
File #: 23-0411    Version: 1
Agenda section: Consent Status: Agenda Ready
File created: 12/19/2022 Meeting type: Baldwin County Commission Regular
On agenda: 1/3/2023 Final action:
Agenda item title: County Road 64 at Baldwin Beach Express Intersection Improvement Project - Design Services
Attachments: 1. Policy #9.10 - Engineering and Survey Services, 2. Map

Meeting Type:   BCC Regular Meeting

Meeting Date:  1/3/2023

Item Status:   New

From: Joey Nunnally, P.E. County Engineer
           Seth Peterson, P.E., Pre-Construction Manager

Submitted by:  John Sedlack, Design Tech III

______________________________________________________________________

 

ITEM TITLE

Title

County Road 64 at Baldwin Beach Express Intersection Improvement Project - Design Services

End

STAFF RECOMMENDATION

Recommendation

Take the following actions:

1) Waive Baldwin County Commission Policy #9.10 - Engineering and Survey Services; and

2) Approve on-call consultant Thompson Engineering to perform design services for the County Road 64 at Baldwin Beach Express Intersection Improvement Project with design fees not to exceed $170,500.00.

End

BACKGROUND INFORMATION

 

Background: 

The Highway Department has selected Thompson Engineering to perform design services for the County Road 64 and Baldwin Beach Express Intersection Improvement Project. The proposed fee of $170,500.00 exceeds the Commission Policy #9.10 Engineering and Survey Services on-call limit of $100,000.00. 

 

Previous Commission action/date: 

December 20, 2022 - Adopted Resolution #2023-035 and approved a Construction Funding Agreement between the Baldwin County Commission and the Alabama Department of Transportation (ALDOT) for the County Road 64 at Baldwin Beach Express Intersection Improvements Project. (This agreement shall be effective upon full execution and shall be in effect until the project and reimbursements are completed.)

 

March 15, 2022 - Authorized the Highway Department to submit an application and documentation for a grant under the Federal Highway Administration - Highway Safety Improvement Program (HSIP) for a proposed Alternate Intersection Design (R-Cut) at County Road 64 and Baldwin Beach Express; and authorized the Chairman to execute a letter of intent and any other grant related documents as required.

 

 

FINANCIAL IMPACT

 

Total cost of recommendation:  $170,500.00

 

Budget line item(s) to be used:  HW22144.1PRECN.1CONTRSRV.1CONTRACT

 

If this is not a budgeted expenditure, does the recommendation create a need for funding?  N/A

 

LEGAL IMPACT

 

Is legal review necessary for this staff recommendation and related documents? 

N/A

 

Reviewed/approved by:  N/A

 

Additional comments:  N/A

 

ADVERTISING REQUIREMENTS

 

Is advertising required for this recommendation?  N/A

 

If the proof of publication affidavit is not attached, list the reason: N/A

 

FOLLOW UP IMPLEMENTATION

 

For time-sensitive follow up, select deadline date for follow up:  N/A

 

Individual(s) responsible for follow up: 

Highway Department will issue a Notice to Proceed to Thompson Engineering to begin design services.

 

Action required (list contact persons/addresses if documents are to be mailed or emailed):  N/A

 

Additional instructions/notes:  N/A